• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/194

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

194 Cards in this Set

  • Front
  • Back

estimate activity durations

process of making educated guesses of the time it will take to complete project activities based on scope, resource assignments, and resource availability

Three-Point Estimate Triangular Distribution Equation

(Optimistic+Most Likely+Pessimistic)/3


Acronym Definition - PERT

Program Evaluation Review Technique

What is Three-Point Estimating?

Average of three estimates to estimate the duration of an activity

What is PERT?

Form of three-point estimating used to estimate the duration of project activities and/or of the project as a whole:


Beta Distribution (O+4ML+P)/6

1 Sigma


2 Sigma


3 Sigma


6 Sigma

1 Sigma = 68.26%


2 Sigma = 95.46%


3 Sigma = 99.73%


6 Sigma = 99.99&

Parkinson's Law

work expands so as to fill the time available for its completion

Develop Schedule

plans the start and finish dates for all project activities using the outputs from the other Time Management planning processes

Schedule Network Analysis

Technique describing the combination of the other tools and techniques in the schedule development process to generate a schedule model

Critical Path Method (CPM)

evaluates schedule start and finish information and logical dependencies to determine the longest path of schedule activities, which then helps determine the shortest possible schedule

Zero Float

the critical path of all activities, any delay will cause an immediate impact on the overall project completion



Early Finish = Early start +1


Late Start = Late finish - 1


Float = Late Start - Early Finish

critical chain method

helps account for resource limitations and project uncertainty


- resource buffers can be placed on paths feeding the critical path and a project buffer to help protect overall completion delay

resource optimization techniques

resource leveling



resource smoothing

modeling techniques

what-if scenario analysis



simulations

schedule compression techniques

crashing - adding resources



fast tracking - overlapping normally sequential activities

Schedule baseline

formal approved version of the schedule model used by the project management team, plus all approved changes



BASELINE = Plan + Approved Changes

BASELINE =

Plan + Approved Changes

Baselines are part of what document?

Project Management Plan

Develop Schedule Outputs

Schedule Baseline


Project Schedule


Schedule Data


Project Calendars


PMP Updates


Project Document Updates

Develop Schedule Inputs

Schedule Management Plan


Activity List


Activity Attributes


Project Schedule Network Diagrams


Activity Resource Requirements


Resource Calendars


Activity Duration Estimates


Project Scope Statement


Risk Register


Project Staff Assignments


Resource Breakdown Structure


Enterprise Environmental Factors


Org. Process Assets

Develop Schedule Tools & Techniques

Schedule Network Analysis


Critical Path Method


Critical Chain Method


Resource Optimization Techniques


Modeling Techniques


Leads and Lags


Schedule Compression


Scheduling Tool

Control Schedule

process of proactively comparing actual project execution to the approved plan to document the performance and influence factors that can bring the project performance closer in line with the plan

Control Schedule Inputs

PMP


Project Schedule


Work Performance Data


Project Calendars


Schedule Data


Org Process Assets

Control Schedule Tools & Techniques

Performance Reviews


Project Mngt Software


Resource Optimization Techniques


Modeling Techniques


Leads and lags


Schedule Compression


Schedule Tool

Work Performance Data

Generated as an output of Direct & Manage Project Work process

Performance Reviews

technique comparing the actual schedule progress against the to detect variations (schedule baseline & work performance data)



work performance information (schedule variance & schedule performance index)

Cost Management

Includes processes to plan and control project spending on resources needed to complete the project work

Plan Cost Management Inputs

PMP


Project Charter


Enterprise Environmental Factors


Org Process Assets

Plan Cost Management Tools & Techniques

Expert Judgement


Analytical Techniques


Meetings

Plan Cost Management Outputs

Cost Mngt Plan

Estimate Costs Inputs

Cost Mngt Plan


HR Mngt Plan


Scope Baseline


Project Schedule


Risk Register


Enterprise Environmental Factors


Org Process Assests

Estimate Costs Tools & Techniques

Expert Judgement


Analagous Estimating


Parametric Estimating


Bottom-up Estimating


Three-point Estimating


Reserve Analysis


Cost of Quality (CoQ)


Project Mngt Software


Vendor Bid Analysis


Group Decision-making techniques


Estimate Costs Outputs

Activity cost estimates


Basis of estimates


Project documents updates

Analagous estimating

use of actual data from similar projects as a basis for predicting durations for future cost estimates

Parametric estimating

use of a mathematical equation to estimate the total cost of an activity based on known quantity and rate information

Bottom-up estimating

uses individual cost estimates for the smallest level of detail and aggregates them up to the higher levels

Reserve Analysis

technique used to counteract risk by adding a buffer into the cost estimate



in this process Contingency Reserve can be added at the activity level based on an identified risk

Cost of Quality (CoQ)

technique used to evaluate all of the costs incurred to ensure desired deliverable quality

Vendor bid analysis

technique of looking at all bids, including the winning bid, to help the project team to understand the value of the work

Activity cost estimates

quantitative data representing expected resource (people, equipment, facilities, and materials) costs for each schedule activity

Budget (Project Funding Requirements)

Management Reserve and Cost Baseline (which includes your contingency reserve)

Basis of estimates

documentation stating how the estimates were generated, assumptions, constraints, and anticipated variances

Estimate Costs

process of making estimates of the costs for each scheduled activity, includes all assumptions



process can be performed iteratively (progress elaboration). The first iteration may develop the "ROM" estimate in the range of -25% to +75%, second iteration may develop a "Definitive Estimate" in the range of -5% to +10%

Determine Budget

process of taking the individual cost estimates and working with stakeholders to generate the overall project cost baseline

Project Budget

Includes:


Mngt Reserve and Cost Baseline



Cost Baseline includes:


contingency reserve and activity cost estimates



cost aggregation

summation of activity cost estimates for each top=level summary

reserve analysis

technique used to counteract risk by adding a buffer into the cost estimate



in this process, "Management Reserve" can be added at the project or phase level based on "unidentified risks"

Cost Baseline

an approved time-phased spending plan for how much and when project assets are authorized to be spent



may include contingency reserves

SPI

Schedule Performance Index:


Measures the schedule efficiency for a time period.


Values greater than 1.0 reflect a pace ahead of schedule (good)

CPI

Cost Performance Index:


Measures cost efficiency for a time period.


Values greater than 1.0 indicate cost underruns (good)

EV

Earned Value:


estimated cost of work actually completed to date (Actual Percent Complete * BAC)

AC

Actual Cost:


total cost of work to date derived form work performance data

BAC

Budget at Completion:


estimated total cost of all project work as documented in the cost baseline

PV

Planned Value:


estimated cost of scheduled work to date (Planned Percent Complete * BAC)

SV

Schedule Variance:


Difference between work completed and what was planned to be completed (EV-PV)

CV

Cost Variance:


difference between the value of work completed and actual spending to date (EV-AC)

EAC

Estimate at Completion:


forecasts total spending based on current rate



BAC/CPI

ETC

Estimate to Completion:


forecasts remaining spending based on current rate



EAC-AC

VAC

Variance at Completion:


the difference between original budget and forecasted total spending



BAC-EAC

TCPI

To-Complete Performance Index:


Forecasts performance needed to achieve a management goal



BAC-EV / BAC-AC

Sponsor

The one who approves the plans, budget, charter

Quality

The degree to which a set of inherent characteristics fulfill requirements

Deming

PDCA - Plan, Do, Check, Act cycle & 85% of quality issues are management related

Kaizen

Japanese for Continuous Improvement

Crosby

cost of nonconformance is high


"do it right the frist time"

Juran's Trilogy

Quality planning, quality control, quality improvements

Taguchi

popularized statistical methods (design of experiments)

Kanban

Just-in-time, reducing inventories to a minimum to meet demand

ISO 9000

set of quality related standards

Quality Mngt Theory & Continuous Improvement

Deming


Kaizen


Crosby


Juran's Trilogy


Taguchi


Kanban


ISO 9000

Seven Basic Quality Tools (Planning Phase)

Cause and Effect Diagram (fishbone or Ishikawa)


Histograms


Pareto Charts


Control Charts


Scatter Diagrams


Flowcharts


Checksheets


Cost of Nonconformance (Bad)


(Cost of Quality)

Scrap


Rework


Warranty


Liability


Loss of Reputation

Cost of Conformance (Good)


(Cost of Quality)

Process Improvement


Training


Upgrading equipment


Taking time/care


Inspections

Cost-Benefit Analysis

technique in which the project team evaluates the benefit of quality so that the cost of quality does not exceed the benefit

Cause and Effect Diagram (fishbone or Ishikawa)

provides a graphical representation of potential factors that can lead to project issues

Histograms

display the statistical distribution of a dataset

Pareto Chart

used to prioritize corrective actions

Rule of Seven

the prospective buyer should hear or see the marketing message at least seven times before they buy it from you

Quality Management Plan

formal documentation describing how the project management team will implement the organization's quality management policies and created deliverables that meet requirements


(subsidiary plan of the PMP)


Output of Plan Quality Management Process

Process Improvement Plan

defines how the value of product development processes can be enhanced - details relationship between the Quality Control and Quality Assurance processes


(subsidiary plan of the PMP)


Output of Plan Quality Management Process

Control Quality buzwords

"deliverable/inspection"


results


product


detective


monitoring


inspection

Quality Assurance buzzwords

"process improvement"


rules


process


policy


preventative


standards

Control Quality

process of monitoring and inspecting deliverables and project management results to evaluate their compliance with quality standards



input to this process is the work product/deliverable from Direct & Manage Project Work process

Verified Deliverables

Deliverables that have been found to confirm to requirements, verified deliverables are an input of the Validate Scope process.



In the case of a defect repair, re-inspection may lead to Validated Changes



(output of control quality)


(input to Validate Scope)

Quality Control Measurements

Data results from inspection which may reveal which defects are most cmmon and provide insight into which processes need to be improved



(Output of Control Quality)


(Input to Perform Quality Assurance)

Perform Quality Assurance

the proactive implementation of quality policy t help the project team achieve continuous improvement and prevent defects - this is the executing process of performing activities that improve quality

Perform Quality Assurance Inputs

Quality Mngt Plan


Process Improvement Plan


Quality Metrics


Quality control measurements


project documents

Perform Quality Assurance Outputs

Change Requests


PMP updates


Project document updates


Org Process Asset Updates

Perform Quality Assurance Tools & Techniques

Quality Mngt and control tools


Quality Audits


Process Analysis

Human Resource Management

Process Group, includes the processes to plan, collect, and manage the project team.

Plan human resource management

process of defining the roles and responsibilities for the project, and staffing how the project team will be acquired, developed, and managed.

Plan human resource management Inputs

PMP


Activity Resource Requirements


Enterprise Environmental Factors


Org Process Assets

Plan human resource management Tools & Techniques

Org Charts & Position Descriptions (Hierarchical Charts and Matrix Charts (RAM))


Networking


Org Theory


Expert Judgement


Meetings

Hierarchical Charts

top-down structure of responsibility

Matrix Charts (RAM)

mapping of responsibility levels to individuals or groups

RACI Matrix

most popular type of RAM


Responsible (R)


Accountable (A)


Consult (C)


Inform(I)

Human Resource Management Plan

includes the staffing management plan, is a subsidiary plan to the PMP, defining when and how resource requirements are met



(output of Plan HR Management process)

Staffing Management Plan

subsidiary plan of the HR Management plan, comprised of:


staff acquisition / release


resource calendars / resource histograms


training needs


rewards and recognition


compliance


safety

Burn Rate

Burn Rate = AC/EV

Acquire Project Team

process of assigning and hiring personnel

Acquire Project Team Inputs

HR Mngt Plan


Enterprise Environmental Factors


Org Process Assets

Acquire Project Team Tools & Techniques

Pre-Assignment


Negotiation


Acquisition


Virtual Teams


Multi-criteria decision analysis

Acquire Project Team Outputs

Project Staff Assignments


Resource Calendars


PMP Updates

Develop Project Team

process of training personnel and conducting teambuilding activities for the purpose of improving project performance

Develop Project Team Inputs

HR Management Plan


Project Staff Assignments


Resource Calendars

Develop Project Team Tools & Techniques

Interpersonal Skills


Training


Teambuilding activities


Ground rules


Colocation


Recognition and rewards


Personnel assignment roles

Develop Project Team Outputs

Team Performance Sheet


Enterprise Environmental Factors

Triple-Constraint Aligned with Formulas

Scope = Earned Value (EV)


Time = Planned Value (PV)


Cost = Actual Costs (AC)

Manage Project Team

Process of assuring that resource efforts are in line with their roles and responsibilities: tracking performance, resolving conflicts, updating plans, and reccommending changes to how resources are utilized

Conflict Management

Problem Solving


Compromising


Smoothing


Withdrawal


Forcing

Problem Solving

provides a win-win resolution, AKA confronting


this is the best method

Compromising

provides a lose-lose resolution

Smoothing

provides a lose-yield situation with no resolution

Withdrawal

provides a lose-leave situation with no resolution (delay tactic)

Forcing

provides a win-lose situation, I win, you lose.


Not a good method.

Project Communications Management

includes processes to ensure the timely distribution, storage, and retrieval of information to facilitate project completion

Plan Communications Management

process of identifying:


what information needs to be shared for successful execution


how that information will be shared


with whom that information will be shared

Lines of Communication

a key indicator to the complexity of the project communication can be investigated by calculating the number of communication channels:



n (n-1) / 2

Communication Requirements Analysis

Technique to determine the need for information of project stakeholders

Communications Management Plan

Output of Plan Communications Management process



Subsidiary plan of the PMP



Documents communication requirements and how the proper communication will be achieved

Manage Communications

process of deploying necessary information to project stakeholders in accordance with the communications management plan



simply the process of following the communication management plan throughout the project lfiecycle

Communication Methods

Interactive - 2 or more parties performing a multi-directional exchange of info. (e.e.g, in person meeting)


Push - Info is sent from one individual to another (e.g., emails and voicemails)


Pull - Info is posted in a place that is available to authorized recipients o access at their own discretion (e.g., online databases)

Control Communications

process of evaluating the execution of communication performance relative to the plan and requesting changes to improve future communications

Control Communicatins Inputs

PMP


Project Communications


Issue Log


Work Performance Data


Org Process Assets

Issue Log

documentation of project conflicts that may exist between the team or stakeholders, the person responsible for solving the problems, and how the issue was resolved

Control Communications Output

Work Performance Information


Change Requests

Monitoring & Controlling Inputs & Outputs

Input - PMP


Input - Work Performance Data


Input - Org Process Assets


Output - Work Performance Information


Output - Change Requests


Output - PMP Updates, Project Document Updates, Org Process Asset Updates

project risk management

processes regarding the planning, monitoring and controlling risk:


identifying, analyzing, planning response and monitoring positive or negative uncertainties

Plan risk management

process of deciding how potential risks will be identified, analyzed, mitigated, and responded to



Output - Risk Management Plan

Risk Management Plan

how to plan and manage project uncertainty


Subsidiary plan to the PMP

Risk Register

a list of identified risks


(output of identify risks process)

Plan risk management Inputs

PMP


Project charter - may contain high-level project risks/assumptions


stakeholder register


Enterprise environmental factors


Org process assets

Plan risk management Tools & Techniques

Analytical techniques


Expert judgement


Meetings

Identify risks

iterative process o assessing what risks the project may be susceptible to.

Identify Risks Inputs

Risk Mngt Plan


Cost Mngt Plan


Schedule Mngt Plan


Quality Mngt Plan


HR Mngt Plan


Scope Baseline


Activity cost estimates


Activity duration estimates


Stakeholder register


Project documents


Procurement documents


Enterprise environmental factors


Org Process Assets


Information Gathering Techniques

Delphi Technique - anonymous survey of SMEs



Root Cause Analysis - technique to identify problems, and the underlying causes for each to better develop a solution

Checklist Analysis

review of lessons learned documentation from previous projects

Assumptions Analysis

review of assumptions that have been made on the project for the purpose of exposing potential risks

Crawford Slip Method

have a piece paper for each person, everyone writes down three risks and submits them, and then review them together



diagramming techniques

graphical methods of discovering risks - cause & effect diagrams, system or process flow charts, and influence diagrams

Nominal Group Technique

a structured method for group brainstorming that encourages contributions from everyone.

Prompt list

Prompting with letters going down the page that can be used to fill in details/risks

SWOT list

examines strengths, weaknesses, opportunities, and threats

Perform Qualitative Risk Analysis

process of prioritizing risks by subjectively evaluating probability of occurrence and impacts to time, cost, scope and quality



(Output is updates to the Risk Register)

Perform Qualitative Risk Analysis

Tools & Techniques:


risk probability assessment


probability and impact matrix


risk data quality assessment


risk categorization


risk urgency assessment


expert judgement


Qualitative ratings

descriptive: low, medium, high



or



numerical ranking: 1-10

Quantitative ratings

Days or Dollars

Quantitative Risk Analysis & Modeling Techniques

sensitivity analysis, expected monetary value analysis, decision trees, and project modeling to generate data that reflects the cost of risk

Expected Monetary Value (EMV)

can be used to predict the value of an event which may or may not occur by evaluating its probability and impact



EMV = Probability * Impact

Decision Trees

used to evaluate risk when the occurrence of a risk event results in multiple possible outcomes

Plan Risk Responses

process of developing strategies to minimize effects of threats and maximize the positive effects

Project Procurement Managment

processes to acquire products or services outside of the organization needed to successfully complete the project - from both buyer and seller prospectives

plan procurement management

process of deciding which project assets need to be purchased, must decide whether or not to purchase, how much and when



TIP - in this process the project team prepares for the other procurement management processes by documenting a structured approach and determining the purchasing requirements

make or buy analysis

technique in plan procurement management to determine if it is more beneficial to the performing organization to produce a product or service in-house or to outsource

market research

include industry trends and capabilities to better understand the options available when purchasing goods and services

Procurement Management Plan

subsidiary plan to the PMP, defines how the other procurement processes will be managed


(Output to Plan procurement Management)

Plan Procurement Management Outputs

Procurement Mngt Plan


Procurement SOWs


Make or Buy Decisions


Procurement Documents


Source Selection Criteria

Procurement Documents

formalized documentation necessary to solicit for seller proposals, can include RFPs to help describe the goods or services required for purchase

Conduct Procurements

process of finding potential sellers through solicitation, evaluating qualifications of those sellers and then selecting sellers and formalizing the terms and conditions

Proposal Evaluation Techniques

Weighting system - data-driven approach where eval criteria are given a weight



Screening system - mandatory requirements that must be met



Seller rating systems - based on past performance

Contract Types

FFP - Seller is at risk


T&M - Buyer is at risk

Control Procurements

process of assuring that both the buyer and seller meets the terms and conditions documented in the agreement between them



this process overlaps many other executing, monitoring, and controlling processes



acceptance of the completed work is done here

Close Procurements

process of each contract being formally closed with the buyer's acceptance of the product/service

How many process areas?

47

List the process groups

Initiating


Planning


Executing


Monitoring & controlling


Closing

List the knowledge areas

Integration Management


Scope Management


Time Management


Cost Management


Quality Management


Stakeholder Management


Procurement Management


HR Management


Communication Management


Risk Management

Project Stakeholder Management

Processes identifying individuals and organization affected by project execution or deliverables and manage their engagement and expectations throughout the project lifecycle

Identify Stakeholders

Inputs - Project charter, Procurement documents, Enterprise Environmental factors, and Org Process Assets



Output - stakeholder register

Plan Stakeholder Management

process of managing how stakeholder expectations will be managed throughout the project lifecycle

Manage stakeholder engagement

process of communicating with the stakeholders to ensure the project execution is in line with their expectations and to proactively address any issues that may exist

Soft Skills of Project Management

Interpersonal skills are behavioral competencies that include communications skills, emotional intelligence, conflict resolution, negotiation, influence, team building and group facilitation

Control Stakeholder Engagement

process of evaluating stakeholder engagement relative to the plan and requesting changes to improve future engagement

1. The final PMP that Roger has been working on has been approved. He and the team are now starting activities to complete the work outlined in the scope statement. Which of the following best describes Roger's current role on the project?

a. developing quality metrics and checklists by using benchmarks and other commercial databases


b. uses the change management system to approve or reject change requests


c. gathers information on status, progress, costs and schedule to document work performance data


d. performs exit criteria to ensure the planning phase is properly closed and update organizational process assets

25. during a project meeting, several members of the change control board have a misunderstanding over the majority vote needed to approve a change request, what project document should the team review to find this information?

a. project charter


b. change mngt plan


c. communications mngt plan


d. HR mngt plan

44. Nicholas has successfully completed his PMP exam and accepted a position as PM. He begins identifying and analyzing the individuals and organizations that will influence or be affected by his project. Which tool would he be most likely to use?

a. probability and impact matrix


b. SWOT analysis


c. salience model


d. variance analysis

55. Which processes are onducted to transition accepted deliverables to the customer and document the project's lessons learned?

a. validate scope


b. monitor & control project work


c. close project or phase


d. control quality

60. which of the following does NOT represent how a project manager should direct and manage the project team to execute the PMP?

a. request changes to improve future scope, cost or schedule performance


b. inspect deliverables to ensure requirements are met


c. document information about the tasks that were started and their progress for future reporting


d. implement approved change requests for defect repair to project work

61. during control schedule and control costs, work performance data is compared with baselines to understand current performance and anticipate future results. What output best describes the prediction of future project performance?

a. analagous estimates


b. forecasts


c. project funding requirements


d. work performance information

65. which of the following activities is most closely related to perform quality assurance process?

a. fixing a list of identified software issues


b. reviewing the trends and measurements found during inspection to analyze project work processes and issue change requests to improve the processes


c. gathering stakeholder requirements and tolerances for quality to create a process improvement plan


d. updating the risk register with potential processes which may contribute to product defects

69. during schedule development, schedule activities not on the critical path may have flexibility to be delayed without delaying the project finish date, this is known as:

a. discretionary dependency


b. total float


c. free float


d. mandatory dependency

87. you have been asked to help prepare a report detailing expected future results based on previous work performance information. What tool and technique will help you to complete this forecasting?

a. monte carlo analysis


b. critical chain


c. earned value technique


d. SWOT technique

88. the planning process group includes processes that plan project executing, monitoring, and controlling, and closing of the project. these processes generate several planning outputs which can be broken down into two main categories, the PMP and project documents. Which of the following is NOT part of the PMP?

a. performance measurement baseline


b. risk register


c. requirements mngt plan


d. configuration mngt plan

97. Which of the following does NOT take place during the conduct procurements process?

a. bidder conferences and advertising


b. proposal evaluation techniques


c. procurement negotiations


d. make or buy analysis


110. when determining the project budget, management reserves should be included in which of the following outputs?

a. cost baseline


b. project funding requirements


c. cost mngt plan


d. funding limit reconciliation

111. procurement mngt defines processes necessary to purchase or acquire products. during which process is payment for the products made from the Buyer to the Seller?

a. close project or phase


b. conduct procurements


c. control procurements


d. close procurements

118. which of the following outcome is NOT included in the close procurement process?

a. archiving contract closure in the records mngt system


b. procurement audits are performed


c. updating lessons learned


d. submitting final payment to the seller

121. in which two calendars are resource calendars an ouput?

a. acquire project team & manage stakeholder engagements


b. estimate activity resources & develop schedule


c. acquire project team & conduct procurements


d. manage stakeholders engagements & control stakeholders engagements

123. which of the following is NOT a true statement concerning precision and accuracy?

a. when a series of measurements is preceise, it means that it is very close to its intended value


b. a series of measurements can be precise without being accurate


c. a series of measurements can be accurate without being precise


d. the project mngt team is in charge of determining the required precision and accuracy on a project

126. when an organization shares characteristics of multiple matrix types (i weak in some regards and strong in others), it is known as:

a. functional organizations


b. silo organizations


c. managed organizations


d. composite organizations

136. there are many tools and techniques in the quality mngt processes. which one examines the repeatability of a process by showing data points with respect to upper and lower limits?

a. statistical sampling


b. histogram


c. fishbone chart


d. control chart

140. Sam (PM) has been informed that his construction project is in an area that is highly susceptible to hurricanes and that this season is predicted to be easily bad. Sam investigates possible responses to this risk and decides to purchase hurricane insurance which would cover any damage experienced. what type of response has Sam chosen?

a. risk mitigation


b. risk avoidance


c. risk transference


d. risk sharing

147. during recent earned value analysis, you have determined that your project is behind schedule, and has a CPI of 1.13. During a performance report to key stakeholders on the CCB, you suggest hiring more resources t help improve schedule performance. What technique have you recommended?

a. fast tracking


b. Delphi technique


c. crashing


d. critical chain scheduling

158. which of the following does NOT describe criteria included for the cost baseline?

a. approved by key stakeholders


b. includes mngt reserve


c. can only be changed through formal change control


d. includes contingency reserve

163. you are using a control chart to determine whether or not a manufacturing process is in control. After reviewing the thousands of data points on the chart, you find that the last ten data points are above the mean and inside of the control limits. How can you best describe this process?

a. the process is in control


b. the process may be out of control, it should be investigated


c. thousands of data points are not enough to determine if the process is in control


d. info about the specification limits is needed to determine if the process is in control