• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/11

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

11 Cards in this Set

  • Front
  • Back

BAC = ____ ?


BAC = Σ (PV )




(Balance at Completion)

EV =

EV = % Complete of BAC




Earned Value is a percentage of the Balance at Completion

AV =

AV = EV- AC




Actual Variance = (Earned Value) - (Actual Costs)

CV

CV = EV - AC




Cost Variance is equal to Earned Value minus Actual Costs.




* Negative variance is cost overrun

SV

SV = EV - PV




Scheduled Variance is equal to Earned Value minus Planned Value




* Negative variance is behind schedule

CPI

CPI = EV / AC




Cost Performance Index is equal to


Earned Value/Actual Costs




* Less than one is cost overrun.

SPI

SPI = EV / PV




Schedule Performance Index is equal to


Earned Value/Planned Value.




* Less than one is behind schedule.

AC

AC=CV / (CPI-1)




Actual Costs is equal to


Cost Variance / (Cost Performance Index - 1)

PV

PV=SV / (SPI-1)Planned Value is equal to Schedule Variance / (Schedule Performance Index - 1)

ETC

ETC = EAC - AC




Estimation to Completion =


(Estimate at Completion) - (Actual Costs)

VAC

VAC = BAC - EAC




Variance at Completion =


(Balance at Completion) - (Estimate at Completion)