• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/90

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

90 Cards in this Set

  • Front
  • Back
What are the 5 Process Groups of Project management?
Initiating
Planning
Executing
Monitoring and Controlling
Closing
What are the 10 Knowledge Areas of Project management?
Integration Management
Scope Management
Time Management
Cost Management
Quality Management
Human Resource Management
Communications Management
Risk Management
Procurement Management
Stakeholders Management
What are 3 different types of organizations?
Functional
Project
Matrix
What are the 3 different types of Matrix Organizations?
Functional Matrix
Project Matrix
Balanced Matrix
What are the 5 stages in a needs requirements lifecycle?
Needs Emergence Phase
Needs Recognition Phase
Needs Articulation Phase
Functional Requirements
Technical Requirements
What are the 3 levels of estimates?
budget, definitive and order of magnitude
What are the components of an integrated project plan?
(11)
Scope Statement
WBS
WBS dictionary
Network Diagram
Resourse Responsibility Matrix
Risk Management Plan
Project Schedule
Project Budget
Risk Response Plan
Quality Plan
Management Plans
Acronym for how to construct an objective statement:
SMART
SMART means...
Specific
Measurable
Attainable
Realistic
Time-related
What does a scope statement do?
Creates common understanding and a basis for decision making
What is the lowest level of a WBS
A work package that breaks the work down into manageable components, organizes the work, and improves the accuracy of the estimates.
Effort Guideline for a work package is
8 - 80 hours
How is the work package written?
as an action, in active voice and with a unique description
What is a Fixed price (Lump Sum) Contract type?
The service provider agrees to provide a defined service for a specific period of time and the client agrees to pay a fixed amount of money for the service.
Unit Price Contract
The project is divided into units and the cost of each is defined. Very flexible method compared to fixed price contract. The contractor decides on the estimates and bidders bid of each element of the project.

The entire project may be given to the same service provider or different units may be allocated to different service providers. This is a good approach when different project units require different expertise to complete.
Cost Plus Contract
The services provider is reimbursed for their machinery, labour and other costs, and the contractor pays an agreed fee to the service provider.
The service provider offers a detailed schedule and the resource allocation for the project. The costs should be properly listed and should be reported to the contractor periodically. The payments may be paid by the contractor at a certain frequency (such as monthly, quarterly) or by the end of milestones.
Incentive Contract
Used when there is some uncertainty in the project cost. This is common for projects involving pilot programs or where new technologies are used.
There are three cost factors in an Incentive contract; target price, target profit and the maximum cost.

The main mechanism of Incentive contract is to divide any target price overrun between the client and the service provider in order to minimize the business risks for both parties.
Retainer (Time and Material - T&M) Contract
The most risk-free contract type where the time and material used for the project are priced.

The contractor only requires knowing the time and material for the project in order to make the payments. This type of contract has short delivery cycles, and for each cycle, separate estimates are sent of the contractor.

Once the contractor signs off the estimate and Statement of Work (SOW), the service provider can start work.

Unlike most of the other contract types, retainer contracts are mostly used for long-term business engagements.
Percentage of Construction Fee
This type of contracts is used for engineering projects. Based on the resources and material required, the cost for the construction is estimated.

Then, the client contracts a service provider and pays a percentage of the cost of the project as the fee for the service provider.

As an example, take the scenario of constructing a house. Assume that the estimate comes up to $230,000.

When this project is contracted to a service provider, the client may agree to pay 30% of the total cost as the construction fee which comes up to $69,000.
What are the processes of Risk Planning?
Risk Identification
Risk Evaluation
Risk Mitigation
Contingency Planning
Response Types to 3 levels of risk
High Risk = ?
Moderate Risk = ?
Low Risk = ?
High Risk - Quantify
Moderate Risk - Respond
Low Risk - Accept & Monitor
Loaded and Unloaded rates:
Staff make 30 /hour but it costs 60/hour What is the overhead rate and what formula is used?
The overhead rate is 100%.
Formula is Indirect costs divided by direct costs..

ie: $100,000 Indirect costs
$50,000 Direct labor

The result is an overhead rate of 2:1, or $2 of overhead for every $1 of direct labor cost incurred.
What is the formula for Loaded rate?
Loaded rate = Unloaded rate ( 1 + overhead rate)
What is crashing?
Adding resources to reduce the duration
What are the 5 different conflict resolution modes – and what do they mean?
(1) Compromising: find a middle-ground alternative. Parties both give a little to get a little.

(2) Avoiding (withdrawal): parties ignore the conflict, try not to get involved or give in easily.

(3) Smoothing (accommodating) strategies: play down differences and stress the importance of common goals.

(4) Confronting (problem solving, integrating, or collaborating) tactics consist of facing the conflict directly and examining possible solutions.

(5) Forcing occurs when one insists, or refuses to consider the other party's position
What are 4 different approaches in the situational leadership model?
Delegating
supporting
coaching
directing OR
(telling, selling, Participating, Delegating)
What is an Order of Magnitude Estimate and when is it used?
-25% to +75%

An Order of Magnitude Estimate would be used at the concept stage of the project when the needs are being articulated and information is starting to be gathered
What is a Budget Estimate and when is it used?
-10% to +25%
As more information is gathered and the scope of the project is understood better, the level of accuracy of the estimate should move closer to that of a Budget Estimate. This is the level of accuracy that is appropriate for a Project Charter and initiating processes because the detailed planning activities have not occurred so there is still a significant level of uncertainty on the project
What is a Definitive Estimate and when is it used?
-5% to +10%
Can be used if the project requirements are very detailed. This is the most accurate estimate that is possible.
What are the 3 different cost estimating techniques?
Analagous, Parametric and Engineering

Analagous

Parametric


Analogous Estimating, AKA Top-down Estimating. Used to determine the duration of the project. After finalizing the high level scope/requirement, the PM will the previously completed projects similar activities with the current activities and determine the duration.

Parametric AKA Statistical estimating:
Parametric Cost Estimating is a structured estimating process which uses statistically based parametric/predictive modeling to provide a basis for high confidence estimates.


Engineering cost estimation is a “bottom up” approach and are the most detailed and costly approach.
PERT formula:
Optimistic + Pessimistic + (Most Likely x 4) / 6
Net Present Value
Present value = Future Value / (1 + r) n

PV = Present Value
FV = Future Value
r = interest rate
n = number of time periods
7 different risk response type:
accept | mitigate | avoid | transfer | exploit | share | enhance
What’s the difference between a condition and a warrantee?
condition is a term of central importance, warrantee not. if you breach a condition, you break the contract, not so with a warrantee, although you can sue later.
7 elements that create a contract:
intent, acceptance, offer, legal purpose, consideration, capacity, lawfulness
If there’s a problem with a deliverable and as a result I go back to the flow chart for how it was produced to look for areas of failure, what’s the process?
QA – auditing
What does OPM3 stand for?
Stands for Organizational Project Management,
5 levels of Maturity (OPM3)
Common Language
Common Processes
Common Methodology
Benchmarking
Continuous Improvement
Responsibility Assignment Matrix is also a...
Paris Chart
PARIS stands for:
Participant - involved but not at a critical level
Accountable - must answer to management for the project task status
Review needed or required
Input needed or required
Sign Off Required
5 stages of team development:
forming, storming, norming, performing, adjourning (tuckman/Jensen)
EV
EV = Actual % complete (in work) * BAC
PV
PV = Planned%Complete(in time) * BAC
CV
Cost Variance:

CV = Earned Value(EV) - Actual Costs(AC)
SV
Schedule Variance:
SV - Earned Value(EV) - Planned Value (PV)
CPI
Cost Performance Index:
CPI = Earned Value(EV) / Actual Costs(AC)
SPI
Schedule Performance Index:
SPI = Earned Value (EV) / Planned Value (PV)
EAC
Estimate at Completion:

EAC = Actual Cost (AC) / %Complete ($)
ETC
Estimate To Completion:
ETC = Estimate At Completion (EAC) - Actual Costs (AC)
VAC
Variance At Completion:
VAC = Budget At Completion (BAC) - Estimate At Completion (EAC)
TCPI
To-Complete Cost Performance Index

TCPI = (BAC - EV)/(BAC - AC)

Or
TCPI = (BAC - EV)/(EAC - AC)
Standard deviation of activity
(P - O) / 6
Variance of activity
[ ( P - O) / 6 ] squared (standard deviation squared)
Total Float
LS - ES

or

LF - EF
EAC
BAC/CPI
# of communication channels
[N * (N-1) ] / 2
What's the difference between the cost budget and a cost baseline?
The cost budget adds management reserves (contingency amount) to the cost baseline
SPI
EV/PV=SPI
ETC
EAC – AC = ETC
VAC
BAC – EAC = VAC
Critical path method:
forward duration,
Backward duration
and slack
Forward Duration= EF-ES+1

Backward duration = LF-LS+1

Slack = LS-ES OR slack= LF-EF
Pareto chart
chart that contains both bars and a line graph, where individual values are represented in descending order by bars, and the cumulative total is represented by the line. Pareto principle (pareto's law; 80-20 rule)- for many events, roughly 80% of the effects come from 20% of the causes. eg., "80% of your sales comes from 20% of your clients". "80% of issues can be fixed by 20% of total efforts/ reasons" etc
Resource Levelling
resource leveling is a project management technique used to examine the use of resources (usually people or equipment) over project time. Resource leveling requires delays task until resources (people/equipment) are available; or add more resources at the expense of (time, cost, scope)
Six sigma management
A business management strategy, originally developed by Motorola in 1986. Six sigma seeks to improve the quality of process outputs by identifying and removing the causes of defects (errors) an minimizing variability in manufacturing and business processes.
PDCA
is an integrative four step management method used for the control and continuous improvement of processes and products. Also known as the Deming cycle
Ishikawa diagrams ( also called fishbone diagrams, herringbone diagrams, cause and effect diagrams, or Fishikawa)
are casual diagrams that show the causes of a specific event. Common uses of the Ishikawa diagram are product design and quality defect prevention, to identify potential factors causing an overall effect.
contracts
FFP,
FPIF,
CPFF,
CPIF,
T&M
more seller risk ( PO,FFP, FPIF, FP-EPA); T&M;

More buyer risk (CPFF, CPIF, CPPC, CPAF)
Fixed price contracts
Purchase orders (PO), Firm fixed price (FFP), Fixed price incentive fee (FPIF), Fixed price economic Adjustments contract (FP-EPA)
RACI
Responsible, Accountable, Consulted, and informed- describes the responsibilities of various roles/ persons in project task or deliverables.
triple constraint
is a model of the constraints of project management: time, cost, scope
Risk response
Risk response negative: avoid, transfer, mitigate, accept; Risk response positive: Share, exploit, enhance, Accept
NPV net present value (Present-Future value formulas)
NPV = (present value of all cash inflows)- (present value of cash out flows)
What does CPI tell us?
how much value we are getting for every dollar spent on the project.
How to caluculate CPI
EV/AC
What is the BAC and when is it defined?
Budget at Completion - defined at the beginning of the project - the amount of $ allocated to the project.
How do I calculate EAC if I know my actual costs and estimated amount to complete the project?
ETC + AC
ETC means?
Estimated remaining costs
What formula for EAC is used if the CPI is abnormal or unreliable?
AC + (BAC-EV)
What does BAC - EV tell me?
How much work (in dollars) still needs to be completed.
What EAC formula do i use if the project is over budget but still needs to meet its deadline? (and why?)
AC + [ (BAC - EV) / (CPI*SPI) ]

Use this formula because it takes the SPI and CPI into consideration
What is the other term for BCWP?
EV

Budgeted cost of work PERFORMED means Earned Value
What is the other term for BCWS?
PV

Budgeted cost of work SCHEDULED means planned value
What is the other term for ACWP?
AC

Actual cost of work performed means Actual Cost
Why do we use Earned Value?
It allows us to:

measure the work performed
measure progress
forecast project cost
forecast data of completion
estimate costs to complete
Earned value is how much work is complete ... when?
at a status date
What does it mean if my SV is negative?
The project is behind schedule
What is the longest path to complete all steps in a project?
the critical path
what kind of tasks have float or slack?
non-critical tasks
What does the forward pass calculate?
the earliest finish data
what does the backward pass calculate?
the critical path and the slack of non-critical tasks