SV
|
Schedule Variance
|
|
CV
|
Cost Variance
|
|
SPI
|
Schedule Performance Index
|
|
CPI
|
Cost Performance Index
|
|
EMV
|
Expected Monetary Value
|
|
Communication Channels Formula
|
n(n-1) / 2
|
|
EAC
|
Estimated at Completion
|
|
BAC
|
Budget at Completion
|
|
ETC
|
Estimated Time to Complete
|
|
VAC
|
Variance at Completion
|
|
EAC Formula
|
BAC / CPI
|
|
ETC Formula
|
Original Time / SPI
|
|
VAC Formula
|
EAC - BAC
|
|
SV Formula
|
EV - PV
|
|
CV Formula
|
EV - AC
|
|
SPI Formula
|
EV / PV
|
|
CPI Formula
|
EV / AC
|
|
3 Point Estimates
|
PM + ML - OP
|
|
PM
ML OP |
Pessimistic
Most Likely Optimistic |
|
Pert
|
PM + (4ML) + OP / 6
|
|
EMV Formula
|
Positve - Negative
|