47 Cards in this Set

  • Front
  • Back
What process group and knowledge area does Develop Project Charter (4.1) belong to?
Initiating process group

Integration Knowledge Area
What process group and knowledge area does Develop Project Management Plan (4.2) belong to?
Planning process group

Integration Knowledge Area
What process group and knowledge area does Direct and Manage Project Work (4.3) belong to?
Executing process group

Integration Knowledge Area
What process group and knowledge area does Monitor and Control Project Work (4.4) belong to?
Monitoring & Controlling process group

Integration Knowledge Area
What process group does Perform
Integrated Change Control (4.5) belong to?
Monitoring & Controlling process group

Integration Knowledge Area
What process group and knowledge area does Close Project or Phase (4.6) belong to?
Closing process group

Integration Knowledge Area
What process group and knowledge area does Plan Scope Management (5.1) belong to?
Planning process group

Scope Management Knowledge Area
What process group and knowledge area does Collect
Requirements (5.2) belong to?
Planning process group

Scope Management Knowledge Area
What process group and knowledge area does Define Scope (5.3) belong to?
Planning process group

Scope Management Knowledge Area
What process group and knowledge area does Create WBS (5.4) belong to?
Planning process group

Scope Management Knowledge Area
What process group and knowledge area does Validate Scope (5.5) belong to?
Monitoring & Controlling process group

Scope Management Knowledge Area
What process group and knowledge area does Control Scope (5.6) belong to?
Monitoring & Controlling process group

Scope Management Knowledge Area
What process group and knowledge area does Plan Schedule Management (6.1) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Define Activities (6.2) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Sequence Activities (6.3) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Estimate Activity Resources (6.4) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Estimate Activity Durations (6.5) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Develop Schedule (6.6) belong to?
Planning process group

Time Management Knowledge Area
What process group and knowledge area does Control Schedule (6.7) belong to?
Monitoring & Controlling process group

Time Management Knowledge Area
What process group and knowledge area does Plan Cost Management (7.1) belong to?
Planning process group

Cost Management Knowledge Area
What process group and knowledge area does Estimate Costs (7.2) belong to?
Planning process group

Cost Management Knowledge Area
What process group and knowledge area does Determine Budget (7.3) belong to?
Planning process group

Cost Management Knowledge Area
What process group and knowledge area does Control Costs (7.4) belong to?
Monitoring & Controlling process group

Cost Management Knowledge Area
What process group and knowledge area does Plan Quality Management (8.1) belong to?
Planning process group

Quality Management Knowledge Area
What process group and knowledge area does Perform Quality Assurance (8.2) belong to?
Executing process group

Quality Management Knowledge Area
What process group and knowledge area does Control Quality (8.3) belong to?
Monitoring & Controlling process group

Quality Management Knowledge Area
What process group and knowledge area does Plan Human Resource Management (9.1) belong to?
Planning process group

Human Resource Management Knowledge Area
What process group and knowledge area does Acquire Project Team (9.2) belong to?
Executing process group

Human Resource Management Knowledge Area
What process group and knowledge area does Develop Project Team (9.3) belong to?
Executing process group

Human Resource Management Knowledge Area
What process group and knowledge area does Manage Project Team (9.4) belong to?
Executing process group

Human Resource Management Knowledge Area
What process group and knowledge area does Plan Communications Management (10.1) belong to?
Planning process group

Project Communications Management Knowledge Area
What process group and knowledge area does Manage Communications (10.2) belong to?
Executing process group

Communications Management Knowledge Area
What process group and knowledge area does Control Communications (10.3) belong to?
Monitoring & Controlling process group

Communications Management Knowledge Area
What process group and knowledge area does Plan Risk Management (11.1) belong to?
Planning process group

Risk Management Knowledge Area
What process group and knowledge area does Identify Risks (11.2) belong to?
Planning process group

Risk Management Knowledge Area
What process group and knowledge area does Perform Qualitative Risk Analysis (11.3) belong to?
Planning process group

Risk Management Knowledge Area
What process group and knowledge area does Perform Quantitative Risk Analysis (11.4) belong to?
Planning process group

Risk Management Knowledge Area
What process group and knowledge area does Plan Risk Responses (11.5) belong to?
Planning process group

Risk Management Knowledge Area
What process group and knowledge area does Control Risks (11.6) belong to?
Monitoring & Controlling process group

Risk Management Knowledge Area
What process group and knowledge area does Plan Procurement Management (12.1) belong to?
Planning process group

Procurement Management Knowledge Area
What process group and knowledge area does Conduct Procurements (12.2) belong to?
Executing process group

Procurement Management Knowledge Area
What process group and knowledge area does Control Procurements (12.3) belong to?
Monitoring & Controlling process group

Procurement Management Knowledge Area
What process group and knowledge area does Close Procurements (12.4) belong to?
Closing process group

Procurement Management Knowledge Area
What process group and knowledge area does Identify Stakeholders (13.1) belong to?
Initiating process group

Stakeholder Management Knowledge Area
What process group and knowledge area does Plan Stakeholder Management (13.2) belong to?
Planning process group

Stakeholder Management Knowledge Area
What process group and knowledge area does Manage Stakeholder Engagement (13.3) belong to?
Executing process group

Stakeholder Management Knowledge Area
What process group and knowledge area does Control Stakeholder Engagement (13.4) belong to?
Monitoring & Controlling process group

Stakeholder Management Knowledge Area