Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
74 Cards in this Set
- Front
- Back
- 3rd side (hint)
Monitor & Control Project Work: Description
|
The process of tracking, reviewing and regulating the progress to meet the performance objectives defined in the project management plan
|
|
|
Monitor & Control Project Work: Inputs
|
1. PMP
2. Performance reports 3. EEF 4. OPA |
|
|
Monitor & Control Project Work: T&T
|
1. Expert judgement
|
|
|
Monitor & Control Project Work: Outputs
|
1. Change requests
2. PMP updates 3. Project document updates |
|
|
Perform Integrated Change Control: Description
|
The process of reviewing all change requests, approving changes and managing changes to the deliverables, OPA, project documents and the PMP
|
|
|
Perform Integrated Change Control: Inputs
|
1. PMP
2. Work performance information 3. Change requests 4. EEF 5. OPA |
|
|
Perform Integrated Change Control: T&T
|
1. Expert judgement
2. Change control meetings |
|
|
Perform Integrated Change Control: Outputs
|
1. Change request status updates
2. PMP updates 3. Project document updates |
|
|
Configuration Activities (3)
|
1. Configuration Identification
2. Configuration status accounting 3. Configuration verification and audit |
|
|
Verify Scope: Description
|
The process of formalizing acceptance of the completed project deliverabels
|
|
|
Verify Scope: Inputs
|
1. PMP
2. Requirements documentation 3. Requirements traceability matrix 4. Validated deliverables |
|
|
Verify Scope: T&T
|
1. Inspection
|
|
|
Verify Scope: Outputs
|
1. Accepted deliverables
2. Change requests 3. Project document updates |
|
|
Components of the scope baseline (3)
|
1. Scope statement
2. WBS 3. WBS dictionary |
|
|
Requirements Traceability Matrix
|
A table that links requirements to their origin and traces them throughout the project life cycle
|
|
|
Control Scope: Description
|
The process of monitoring the status of the project and product scope and managing changes to the scope baseline
|
|
|
Control Scope: Inputs
|
1. PMP
2. Work performance information 3. Requirements documentation 4. Requirements traceability matrix 5. OPA |
|
|
Control Scope: T&T
|
1. Variance analysis
|
|
|
Control Scope: Outputs
|
1. Work performance measurements
2. OPA updates 3. Change requests 4. PMP updates 5. Project document updates |
|
|
PMP uses these to control scope (5)
|
1. Scope baseline
2. Scope mgt plan 3. Change mgt plan 4. Configuration mgt plan 5. Requirements mgt plan |
|
|
2 PMP Updates (Output to Control Scope)
|
1. Scope baseline - if approved change requests affect scope, then scope statement, WBS and WBS dictionary have revised and reissued.
2. Other baseline updates - if approved change affect scope, then cost baseline and schedule baseline are revised and reissued. |
|
|
Control Schedule: Description
|
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline
|
|
|
Control Schedule: Inputs
|
1. PMP
2. Project schedule 3. Work Performance Information 4. OPA |
|
|
Control Schedule: T&T
|
1. Performance Reviews
2. Variance Analysis 3. Project Mgt Software 4. Resource Leveling 5. What-if scenario analysis 6. Adjusting Leads and Lags 7. Schedule compression 8. Scheduling Tool |
|
|
Control Schedule: Outputs
|
1. Work Performance Measurements
2. OPA 3. Change requests 4. PMP updates 5. Project document updates |
|
|
Control Costs: Description
|
The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline
|
|
|
Control Costs: Inputs
|
1. PMP
2. Project funding requirements 3. Work Performance Information 4. OPA |
|
|
Control Costs: T&T
|
1. Earned Value Mgt
2. Forecasting 3. To-complete performance index 4. Performance reviews 5. Variance analysis 6. Project mgt software |
|
|
Control Costs: Outputs
|
1. Work performance measurements
2. Budget forecasts 3. OPA updates 4. Change requests 5. PMP updates 6. Project document updates |
|
|
Two Inputs the to PMP used to control cost
|
1. Cost performance Baseline
2. Cost Mgt Plan |
1. Cost performance baseline is compared with actual results to determine if a change, corrective action or preventive action is necessary
2. Cost Mgt Plan describes how the project costs will be managed and controlled |
|
Work Performance Information
|
Information about project progress, such as which deliverables have started, their progress and which deliverables have finished. Also includes costs that have been authorized and incurred, and estimates for completing project work
|
|
|
Earned Value Management
|
Method of performance measurement which integrates scope, cost and schedule measures to help the project mgt team assess and measure project performance and progress
|
|
|
Planned Value
|
The authorized budget assigned to the work to be accomplished for an activity or work breakdown structure component.
|
|
|
Earned Value
|
The value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component
|
|
|
Actual Cost (AC)
|
The total cost actually incurred and recorded in accomplishing work performed for an activity or WBS component.
|
|
|
Schedule Variance (SV)
|
A measure of schedule performance on a project.
Equation: |
SV = EV - PV
|
|
Cost Variance (CV)
|
A measure of cost performance on a project.
Equation: |
CV = EV -AC
|
|
Schedule Performance Index (SPI)
|
A measure of progress achieved compared to progress planned on a project.
Equation: |
SPI = EV/PV
|
|
Cost Performance Index (CPI)
|
A measure of of the value of work completed compared to the actual costs or progress made on the project.
Equation: |
CPI = EV/AC
|
|
Manual Estimate at Completion (EC)
|
The project managers bottom-up EAC which is used to compare with the other EAC methods.
Equation: |
EAC = AC + bottom-up ETC
|
|
EAC Forecast for ETC work performed at the budgeted rate
|
EAC method which accepts the actual project performance to date and predicts that all future ETC work will be accomplished at the budgeted rate.
Equation: |
EAC = AC + BAC - EV
|
|
EAC Forecast for ETC work performed at the present CPI
|
EAC method which assumes what the project has exerienced to date can be expected to continue in the future (same CPI)
|
EAC = BAC/cumulative CPI
|
|
EAC Forecast for ETC work considering both SPI and CPI factors
|
EAC method in which the ETC will be performed at an efficiency rate that considers both the cost and schedule performance indices. Most useful when the project schedule is a factor impacting the ETC effort.
Equation: |
EAC = AC + [(BAC-EV)] / (cumulative CPI x cumulative SPI)]
|
|
To-Complete Performance Index (TCPI)
|
The calculated projection of cost performance that must be achieved on the remaining work to meet a specified mgt goal, such as the BAC or EAC.
Equation: |
Based on BAC: TCPI = (BAC-EV) / (BAC - AC)
Based on EAC: TCPI = (BAC-EV) / (EAC - AC) |
|
Variance Analysis
|
Used in EVM, compares actual project performance to planned or expected performance
|
|
|
Trend Analysis
|
Examines project performance over time to determine if performance is improving or deteriorating.
|
|
|
Earned Value Performance
|
EVM compares the baseline plan to actual schedule and cost performance
|
|
|
Perform Quality Control: Description
|
The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes
|
|
|
Perform Quality Control: Inputs
|
1. PMP
2. Quality Metrics 3. Quality checklists 4. Work performance measurements 5. Approved change requests 6. Deliverables 7. OPA |
|
|
Perform Quality Control: T&T
|
1. Cause and Effect diagrams
2. Control charts 3. Flowcharting 4. Histogram 5. Pareto chart 6. Run chart 7. Scatter diagram 8. Statistical sampling 9. Inspection 10. Approved change requests review |
|
|
Perform Quality Control: Outputs
|
1. Quality control measurements
2. Validated changes 3. Validated deliverables 4. OPA updates 5. Change requests 6. PMP updates 7. Project document updates |
|
|
Cause and Effect Diagrams
|
Illustrate how various factors might be linked to potential problems or effect.
AKA: |
Ishikawa or Fishbone
|
|
Control Charts
|
The appropriate data is collected and analyzed to indicate the quality status of project processes and products. How a process behaves over time.
|
|
|
Flowcharting
|
Used during perform quality control to determine a failing process step(s) and identify potential process improvement opportunities
|
|
|
Histogram
|
A vertical bar chart showing how often a particular variable state occurred. Helps illustrate the most common cause of problems in a process.
|
|
|
Pareto Chart
|
A specific type of histogram, ordered by frequency of occurrence, which show how many defects were generated by type or category of identified cause
|
|
|
Run Chart
|
Similar to a control chart, it shows the history and pattern of variation. A line graph with plotted data points. Trend Analysis.
Used to monitor (2): |
1. Technical Performance
2. Cost and schedule performance |
|
Scatter Diagram
|
Shows the relationship between two variables. Dependant variables vs independent variables.
|
|
|
Report Performance: Description
|
The process of collecting and distributing performance information, including status reports, progress measurements and forecasts
|
|
|
Report Performance: Inputs
|
1. PMP
2. Work performance information 3. Work performance measurements 4. Budget forecasts 5. OPA |
|
|
Report Performance: T&T
|
1. Variance Analysis
2. Forecasting methods 3. Communication methods 4. Reporting systems |
|
|
Report Performance: Outputs
|
1. Performance reports
2. OPA updates 3. Change requests |
|
|
Time Series Methods
|
Forecasting methods which use historical data as the basis for estimating future outcomes.
Examples: |
Earned Value
Moving Average Extrapolation Linear prediction Trend estimation Growth Curve |
|
Causal/Econometric Methods
|
Forecasting methods that use the assumption that it is possible to identify the underlying factors that might influence the variable that is being forecasted. For instance, rain..unbrellas.
Examples: |
Regression analysis
Autoregressive moving Average (ARMA) Econometrics |
|
Judgmental Methods
|
Forecasting methods which incorporate intuitive judgements, opinions and probability estimates.
Examples: |
Delphi Method
Scenario Building Technology Forecasting Forecast by Analogy |
|
Monitor & Control Risks: Description
|
The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk process effectiveness throughout the project
|
|
|
Monitor & Control Risks: Inputs
|
1. Risk Register
2. PMP 3. Work performance information 4. Performance Reports |
|
|
Monitor & Control Risks: T&T
|
1. Risk assessment
2. Risk audits 3. Variance and trend analysis 4. Technical performance measurement 5. Reserve analysis 6. Status meetings |
|
|
Monitor & Control Risks: Outputs
|
1. Risk register updates
2. OPA updates 3. Change requests 4. PMP updates 5. Project document updates |
|
|
Administer Procurements: Description
|
The process of managing procurement realtionships, monitoring contract performance and making changes and corrections as needed
|
|
|
Administer Procurements: Inputs
|
1. Procurement Documents
2. PMP 3. Contract 4. Performance Reports 5. Approved change requests 6. Work performance information |
|
|
Administer Procurements: T&T
|
1. Contract change control system
2. Procurement performance reviews 3. Inspections and audits 4. Performance reporting 5. Payment systems 6. Claims administration 7. Records management system |
|
|
Administer Procurements: Outputs
|
1. Procurement documentation
2. OPA updates 3. Change requests 4. PMP updates |
|
|
Contract Control System
|
Defines the process by which the procurement can be modified
|
|