• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/74

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

74 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
Monitor & Control Project Work: Description
The process of tracking, reviewing and regulating the progress to meet the performance objectives defined in the project management plan
Monitor & Control Project Work: Inputs
1. PMP
2. Performance reports
3. EEF
4. OPA
Monitor & Control Project Work: T&T
1. Expert judgement
Monitor & Control Project Work: Outputs
1. Change requests
2. PMP updates
3. Project document updates
Perform Integrated Change Control: Description
The process of reviewing all change requests, approving changes and managing changes to the deliverables, OPA, project documents and the PMP
Perform Integrated Change Control: Inputs
1. PMP
2. Work performance information
3. Change requests
4. EEF
5. OPA
Perform Integrated Change Control: T&T
1. Expert judgement
2. Change control meetings
Perform Integrated Change Control: Outputs
1. Change request status updates
2. PMP updates
3. Project document updates
Configuration Activities (3)
1. Configuration Identification
2. Configuration status accounting
3. Configuration verification and audit
Verify Scope: Description
The process of formalizing acceptance of the completed project deliverabels
Verify Scope: Inputs
1. PMP
2. Requirements documentation
3. Requirements traceability matrix
4. Validated deliverables
Verify Scope: T&T
1. Inspection
Verify Scope: Outputs
1. Accepted deliverables
2. Change requests
3. Project document updates
Components of the scope baseline (3)
1. Scope statement
2. WBS
3. WBS dictionary
Requirements Traceability Matrix
A table that links requirements to their origin and traces them throughout the project life cycle
Control Scope: Description
The process of monitoring the status of the project and product scope and managing changes to the scope baseline
Control Scope: Inputs
1. PMP
2. Work performance information
3. Requirements documentation
4. Requirements traceability matrix
5. OPA
Control Scope: T&T
1. Variance analysis
Control Scope: Outputs
1. Work performance measurements
2. OPA updates
3. Change requests
4. PMP updates
5. Project document updates
PMP uses these to control scope (5)
1. Scope baseline
2. Scope mgt plan
3. Change mgt plan
4. Configuration mgt plan
5. Requirements mgt plan
2 PMP Updates (Output to Control Scope)
1. Scope baseline - if approved change requests affect scope, then scope statement, WBS and WBS dictionary have revised and reissued.
2. Other baseline updates - if approved change affect scope, then cost baseline and schedule baseline are revised and reissued.
Control Schedule: Description
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline
Control Schedule: Inputs
1. PMP
2. Project schedule
3. Work Performance Information
4. OPA
Control Schedule: T&T
1. Performance Reviews
2. Variance Analysis
3. Project Mgt Software
4. Resource Leveling
5. What-if scenario analysis
6. Adjusting Leads and Lags
7. Schedule compression
8. Scheduling Tool
Control Schedule: Outputs
1. Work Performance Measurements
2. OPA
3. Change requests
4. PMP updates
5. Project document updates
Control Costs: Description
The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline
Control Costs: Inputs
1. PMP
2. Project funding requirements
3. Work Performance Information
4. OPA
Control Costs: T&T
1. Earned Value Mgt
2. Forecasting
3. To-complete performance index
4. Performance reviews
5. Variance analysis
6. Project mgt software
Control Costs: Outputs
1. Work performance measurements
2. Budget forecasts
3. OPA updates
4. Change requests
5. PMP updates
6. Project document updates
Two Inputs the to PMP used to control cost
1. Cost performance Baseline
2. Cost Mgt Plan
1. Cost performance baseline is compared with actual results to determine if a change, corrective action or preventive action is necessary
2. Cost Mgt Plan describes how the project costs will be managed and controlled
Work Performance Information
Information about project progress, such as which deliverables have started, their progress and which deliverables have finished. Also includes costs that have been authorized and incurred, and estimates for completing project work
Earned Value Management
Method of performance measurement which integrates scope, cost and schedule measures to help the project mgt team assess and measure project performance and progress
Planned Value
The authorized budget assigned to the work to be accomplished for an activity or work breakdown structure component.
Earned Value
The value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component
Actual Cost (AC)
The total cost actually incurred and recorded in accomplishing work performed for an activity or WBS component.
Schedule Variance (SV)
A measure of schedule performance on a project.

Equation:
SV = EV - PV
Cost Variance (CV)
A measure of cost performance on a project.

Equation:
CV = EV -AC
Schedule Performance Index (SPI)
A measure of progress achieved compared to progress planned on a project.

Equation:
SPI = EV/PV
Cost Performance Index (CPI)
A measure of of the value of work completed compared to the actual costs or progress made on the project.

Equation:
CPI = EV/AC
Manual Estimate at Completion (EC)
The project managers bottom-up EAC which is used to compare with the other EAC methods.

Equation:
EAC = AC + bottom-up ETC
EAC Forecast for ETC work performed at the budgeted rate
EAC method which accepts the actual project performance to date and predicts that all future ETC work will be accomplished at the budgeted rate.

Equation:
EAC = AC + BAC - EV
EAC Forecast for ETC work performed at the present CPI
EAC method which assumes what the project has exerienced to date can be expected to continue in the future (same CPI)
EAC = BAC/cumulative CPI
EAC Forecast for ETC work considering both SPI and CPI factors
EAC method in which the ETC will be performed at an efficiency rate that considers both the cost and schedule performance indices. Most useful when the project schedule is a factor impacting the ETC effort.

Equation:
EAC = AC + [(BAC-EV)] / (cumulative CPI x cumulative SPI)]
To-Complete Performance Index (TCPI)
The calculated projection of cost performance that must be achieved on the remaining work to meet a specified mgt goal, such as the BAC or EAC.

Equation:
Based on BAC: TCPI = (BAC-EV) / (BAC - AC)

Based on EAC: TCPI = (BAC-EV) / (EAC - AC)
Variance Analysis
Used in EVM, compares actual project performance to planned or expected performance
Trend Analysis
Examines project performance over time to determine if performance is improving or deteriorating.
Earned Value Performance
EVM compares the baseline plan to actual schedule and cost performance
Perform Quality Control: Description
The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes
Perform Quality Control: Inputs
1. PMP
2. Quality Metrics
3. Quality checklists
4. Work performance measurements
5. Approved change requests
6. Deliverables
7. OPA
Perform Quality Control: T&T
1. Cause and Effect diagrams
2. Control charts
3. Flowcharting
4. Histogram
5. Pareto chart
6. Run chart
7. Scatter diagram
8. Statistical sampling
9. Inspection
10. Approved change requests review
Perform Quality Control: Outputs
1. Quality control measurements
2. Validated changes
3. Validated deliverables
4. OPA updates
5. Change requests
6. PMP updates
7. Project document updates
Cause and Effect Diagrams
Illustrate how various factors might be linked to potential problems or effect.

AKA:
Ishikawa or Fishbone
Control Charts
The appropriate data is collected and analyzed to indicate the quality status of project processes and products. How a process behaves over time.
Flowcharting
Used during perform quality control to determine a failing process step(s) and identify potential process improvement opportunities
Histogram
A vertical bar chart showing how often a particular variable state occurred. Helps illustrate the most common cause of problems in a process.
Pareto Chart
A specific type of histogram, ordered by frequency of occurrence, which show how many defects were generated by type or category of identified cause
Run Chart
Similar to a control chart, it shows the history and pattern of variation. A line graph with plotted data points. Trend Analysis.

Used to monitor (2):
1. Technical Performance
2. Cost and schedule performance
Scatter Diagram
Shows the relationship between two variables. Dependant variables vs independent variables.
Report Performance: Description
The process of collecting and distributing performance information, including status reports, progress measurements and forecasts
Report Performance: Inputs
1. PMP
2. Work performance information
3. Work performance measurements
4. Budget forecasts
5. OPA
Report Performance: T&T
1. Variance Analysis
2. Forecasting methods
3. Communication methods
4. Reporting systems
Report Performance: Outputs
1. Performance reports
2. OPA updates
3. Change requests
Time Series Methods
Forecasting methods which use historical data as the basis for estimating future outcomes.

Examples:
Earned Value
Moving Average
Extrapolation
Linear prediction
Trend estimation
Growth Curve
Causal/Econometric Methods
Forecasting methods that use the assumption that it is possible to identify the underlying factors that might influence the variable that is being forecasted. For instance, rain..unbrellas.

Examples:
Regression analysis
Autoregressive moving Average (ARMA)
Econometrics
Judgmental Methods
Forecasting methods which incorporate intuitive judgements, opinions and probability estimates.

Examples:
Delphi Method
Scenario Building
Technology Forecasting
Forecast by Analogy
Monitor & Control Risks: Description
The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk process effectiveness throughout the project
Monitor & Control Risks: Inputs
1. Risk Register
2. PMP
3. Work performance information
4. Performance Reports
Monitor & Control Risks: T&T
1. Risk assessment
2. Risk audits
3. Variance and trend analysis
4. Technical performance measurement
5. Reserve analysis
6. Status meetings
Monitor & Control Risks: Outputs
1. Risk register updates
2. OPA updates
3. Change requests
4. PMP updates
5. Project document updates
Administer Procurements: Description
The process of managing procurement realtionships, monitoring contract performance and making changes and corrections as needed
Administer Procurements: Inputs
1. Procurement Documents
2. PMP
3. Contract
4. Performance Reports
5. Approved change requests
6. Work performance information
Administer Procurements: T&T
1. Contract change control system
2. Procurement performance reviews
3. Inspections and audits
4. Performance reporting
5. Payment systems
6. Claims administration
7. Records management system
Administer Procurements: Outputs
1. Procurement documentation
2. OPA updates
3. Change requests
4. PMP updates
Contract Control System
Defines the process by which the procurement can be modified