• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/26

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

26 Cards in this Set

  • Front
  • Back
Most people seem to believe that the number one behavioral issue in project management is multiple-boss reporting.
A. True
B. False
A
Which of the following is not a personal attribute of a project manager?
A. Honesty and integrity
B. Energy and toughness
C. Poor coping skills
D. Decision-making skills
C
Project manager selection is usually made by the:
A. Senior levels of management
B. Customer’s selection process
C. Line management based upon cooperation on past projects
D. Voting by the team members
A
Which of the following is a job-related characteristic that a PM should possess or may be expected to possess?
A. Necessity for feasibility studies
B. Project’s priority and risks.
C. Requirement for complex technical expertise
D. All of the above
D
The wrong people are often selected as project managers because of:
A. A belief that project management maturity comes with age
B. A belief that someone who knows the customer well will make the best project manager
C. A belief that entrepreneurial skills are always necessary
D. all of the above
D
It is usually easier to manage one large project on a full-time basis than to manage multiple small projects at the same time.
A. True
B. False
A
Which of the following is often regarded as the best way to train project managers?
A. On-the-job-training
B. Formal education
C. Seminars
D. Personal readings
A
According to the text, the “next generation” project manager must exhibit skills in all of the following except:
A. Integration skills
B. Risk management skills
C. Wage and salary administration skills
D. Knowledge of the business
C
Which of the following is usually not a major concern for the PM during the organizational staffing process?
A. Union vs nonunion personnel
B. Where the resources will come from
C. Skill level of the resources
D. Type of organizational structure for the project?
A
Probably the greatest risk to a project manager on a long-term project is to receive the best employees and then:
A. Have them seek perfection rather than just meeting the requirements
B. Find that your costs are escalating
C. Being unable to motivate them.
D. Losing them to other projects at an inopportune time
D
In a weak matrix structure, teamwork is not vital for project success because the team members are under the control of their functional manager.
A. True
B. False
B
Which people generally receive no visibility or credit for a job well done.
A. Project sponsors
B. Project managers
C. Project team members
D. Functional managers
D
Strange as it may seem, project managers should encourage conflicts to take place during recruitment and staffing.
A. True
B. False
A
Under which of the following situations should an employee be terminated from the project?
A. Failure to follow rules, policies and procedures
B. Failure to accept formal authority
C. Professionalism more important than company loyalty.
D. all of the above
D
Which of the following is not usually an option for a PM dealing with an incompetent worker?
A. On-the-spot appraisals
B. Re-assignment to less critical activities
C. Removal from the company
D. Removal from the project
C
Which of the following is not usually an option for a PM dealing with an incompetent worker?
A. On-the-spot appraisals
B. Re-assignment to less critical activities
C. Removal from the company
D. Removal from the project
C
A typical project office (not to be confused with a project management office) responsible for the management of a large project includes the project manager and the:
A. Project sponsor
B. Project sponsor and assistant project managers
C. Assistant project managers
D. Assistant project managers and functional managers
C
During the past few years, which project management skill seems to have outpaced all other skills?
A. Technical skills
B. Business conceptual skills
C. Behavioral skills
D. Problem-solving skills
B
Professionally-trained people with advanced degrees often prefer:
A. To work on project tasks alone
B. To work in groups with people devoted to their discipline
C. To work in groups with people not devoted to their discipline
D. Never to work on project teams
B
Project team members often feel threatened by the possibility of the cancellation of the project. In which organizational form is this threat the greatest?
A. Projectized
B. Strong matrix
C. Balanced matrix
D. Weak matrix
A
Some companies assign employees to a project management position as a lateral transfer move without a salary increase because:
A. The project is short term in nature
B. The project maybe cancelled
C. The employee must demonstrate performance first
D. The employee reports to a functional organization
C
The person most qualified to assess the overall risk in a work package activity in a project is the:
A. PM
B. Sponsor
C. Team member
D. Team member and / or line manager
D
Once an employee is assigned to a project, the project manager has the authority to provide team members with work assignments above their pay grade so that they can get promoted.
A. True
B. False
B
Who determines grade level of the employee needed to accomplish a task?
A. Project sponsor
B. Project manager
C. Functional manager
D. A consensus vote during the project’s kickoff meeting.
C
You have just been awarded a contract in which you told the customer that a certain employee would be assigned full time on the project. Once the project begins, you discover that the employee is splitting his time between two projects per the instructions of his functional manager. You should:
A. Do nothing
B. Determine the impact on the project and discuss it with the project sponsor
C. Determine the impact on the project and discuss it with the functional manager
D. Determine the impact on the project and discuss it with the customer
C
After contract award, a customer requests that some of the senior workers in the functional areas be assigned to the project team. You priced out the project assuming the average worker would be assigned and furthermore assumed that the average worker could do the job effectively. You should discuss this first with:
A. The average workers
B. The senior workers
C. The project sponsor
D. The functional manager
C