Category II nonfriable ACM means any material except Category I nonfriable ACM.
|
A. True
B. False |
A. True
|
|
Notification to NESHAP for demolition or renovation is required when removing less than 160 square feet of RACM.
|
A. True
B. False |
A. True
|
|
RACM doesn’t need to be removed during demolition if:
|
A. It was not accessible for testing
B. The material cannot be safely removed C. A and B D. Neither A nor B |
C. A and B
|
|
It is a requirement that at least one management-level person be trained in the NESHAP regulations and be present on site during RACM disturbance.
|
A. True
B. False |
A. True
|
|
Category II nonfriable ACM with a low probability that the materials will become crumbled, pulverized, or reduced to powder during demolition must be removed prior to demolition.
|
A. True
B. False |
B. False
|
|
Leak-tight also means dust-tight.
|
A. True
B. False |
A. True
|
|
Wrecking, or taking out, any load-supporting structural member is considered demolition.
|
A. True
B. False |
A. True
|
|
A ship is considered a:
|
A. Large boat
B. Industrial unit C. Facility D. None of the above |
C. Facility
|
|
If a facility is demolished by intentional burning, all RACM including Category I and Category II nonfriable ACM must be removed in accordance with the NESHAP before burning.
|
A. True
B. False |
A. True
|
|
Facility component means any part of a facility excluding equipment.
|
A. True
B. False, it includes equipment |
B. False, it includes equipment
|
|
Any building, structure, or installation that contains a loft used as a dwelling is not considered a residential structure, installation, or building.
|
A. True
B. False |
A. True
|
|
Waste generator means any owner or operator of a source whose act or process produces asbestos-containing waste material.
|
A. True
B. False |
A. True
|
|
Notification to NESHAP for demolition or renovation is not required when removing less than 35 cubic feet of RACM.
|
A. True
B. False |
B. False
|
|
Demolition or renovation activities can begin before all of the asbestos is removed.
|
A. True
B. False |
A. True
|
|
When working on a two story 100 unit apartment complex, the bagged RACM can be:
|
A. Lowered to the floor or ground
B. Dropped to the lower floor or ground C. Thrown down the stairs D. All of the above |
A. Lowered to the floor or ground
|