• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/65

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

65 Cards in this Set

  • Front
  • Back
Maymac Environmental Services Ltd v Faraday Building Services Ltd (2000)
Implied agreement as to existence of contract as parties had agreed to adjudicate on it.
Whiteways Contractors (Sussex) Ltd v Impresa Castelli Construction (UK) Ltd (2000)
Requesting an adjudicator to determine his juriisdiction gives him authority to do so.
Discain Project Services Ltd v Opecprime Development Ltd (2001)
Telephone communications with one party about substantive issues need to be fully recorded and sent to the other party for comments.
Porter v McGill (2002)
Fair minded observer used
Dean & Dyball Construction Ltd v Kenneth Grubb Associates Ltd (2003)
Both parties must be informed of the substance of communication the adjudicator receives and be given the opportunity to comment on it, for the sake of natural justice.
London and Amsterdam Properties Ltd v Waterman Partnership Ltd (2004)
Late information can be excluded if insufficient time allowed for the parties to consider it and respond.
Balfour Beatty Construction Northern Ltd v. Modus Corovest (Blackpool) Ltd (2008)
Coulson noted that 'an adjudicator is not obliged to decide each and every point argued, but only those that are genuinely ' en-route' to deciding an underlying dispute between parties.'
Amec Capital Projects Ltd v. Whitefriars City Estates Ltd (2004)
- Fair minded and informed observer test used for adjudication to determine bias allegations.
- Only properly arguable objections should be used for allegations of lack of natural justice.
- If one adjudication was a nullity, it can be heard again in a subsequent adjudication
Pegram Shopfitters Ltd v Tally Weijl (UK) Ltd (2003)
Parties can agree to be bound by the adjudicators decision

Adjudicator wrongly appointed so lack of jurisdiction.
Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd (2009)
Decisions must be intelligible and not wholly unreasoned if reasons are required.
Project Consultancy Group Ltd v The Trustees of the Gray Trust (1999)
'Ad hoc' jurisdiction rights can be inferred by parties requesting adjudication, unless reserved objections are made initially.
Cowlin Construction Ltd v CFW Architects (2003)
Professional fees and professional negligence claims are suitable for adjudication.
Glencot Development and Design v Ben Barrett & Son (Contractors) Ltd (2001)
Adjudicators decision creates a contractual obligation for parties to comply. Scheme 23(2), Act 108(3). Enforcement is for that contractual breach.

Perceived bias established by mediating prior to adjudicating.
Griffin (t/a K&D Contractors) v. Midas Homes Ltd (2000)
The adjudicator only has jurisdiction to determine the dispute set out in the notice of adjudication.
AC Yule & Son Ltd v Speedwell Roofing & Cladding Ltd [2007]
-​An extension of time request may be acquiesced by conduct or silence. It can only be refused by making it clear.
Ale Heavy Lift v MSD (Darlington) Ltd [2006] EWHC
Where jurisdictional challenge on a ground not made then later challenge deemed waived.
Amec Civil Engineering Ltd v Secretary of State for Transport [2004] EWCA
7 propositions;
'Dispute' should be given it's normal meaning.
Litigation has not generated any hard egded definition but has given some good guidance.
Non-admission or denial, rather than just notification gives rise to a dispute.
Non-admission circumstances are Protean. Silence may suffice.
Silence forming dispute must depend on circumstances to be valid.
deadlines for responses are not automatically accepted but may be relevant factors in court.
Ill defined or nebulous claims that cannot reasonably be responded to are unlikely to give rise to disputes.
ASM Shipping Ltd v TTMI ltd [2005] EWHC
Arbitrator continued although later deemed to have a conflict of Interest from recent unrelated case with previously known witnesses accused of impropriety. Judge concluded he should have withdrawn.
Aveat Heating Ltd v Jerram Falkus Construction Ltd [2007]
-​The Scheme replaces all of the adjudication provisions where the contract does not comply with 108 of the HGCR the Act, unless it also gives provision for how that would work.

-​Fractions of the day were to be ignored in calculating the period for decisions.

-​Referral receipt commences the 28 day deadline.
Balfour Beatty Construction Ltd v London Borough of Lambeth [2002]
-​A critical path analysis was done and criticised by courts for 'making the case' for a party. The work was not disclosed to the parties for comment.

-​If a decision cannot be made in time and additional time is not given then the adjudicator should resign.
Barnes & Elliott Ltd v Taylor Woodrow Holdings Ltd & Wimpey Southern [2003]
-​Decision one day late was still enforceable under contract.
Grovedeck Ltd v. Capital Demolition Ltd [2000] BLR 181
Contractual clauses can allow for multiple disputes or contracts under the Act but not if the Scheme applies.
Sherwood & Casson Ltd v. MacKenzie Engineering Ltd (2000)
Adjudicator must resign if dispute is substantially similar to a previously determined one.
Beck Pepiatt Ltd v Norwest Holst Construction Ltd [2003]
-​'Dispute' is to be given it's ordinary meaning.
Bloor Construction (UK) Ltd v Bowmer & Kirkland (London) Ltd [2000]
-​The adjudicator has implied powers to correct an error or remove an ambiguity provided it is an accidental error/omission which reflects his original intention and that it is made within a reasonable time and without prejudicing the other party.
Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2000]
- ​If a decision answered the right question but contained errors of arithmetic, it will still be enforceable.
Bridgeway Construction Ltd v Tolent Construction Ltd [2000] CILL
Express clause stated that referring party should pay all costs. Courts upheld clause.
Cantillon Ltd v Urvasco Ltd BLR 250, [2008] EWHC 282 (TCC)
The responding party is entitled to raise any defence to the claim being made, that is legal, and the adjudicator must consider it.
Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2005]
-​Court determined that the dispute had not crystallised before the adjudication notice.

-​Interest cannot be awarded unless specifically asked for or is in the contract terms.

-​Adjudicator does not have the jurisdiction to determine a dispute which was made orally even though the contract itself is in writing.

-​If the adjudicator declined to consider evidence which he felt was irrelevant that was neither a breach of natural justice nor a failure to consider relevant material.
Christiani & Neilsen Ltd v Lowry Centre Development Co Ltd [2000]
-​Adjudicators have the right to enquire as to their own jurisdiction.

-​Parties cannot 'contract out' of the terms of the HGCRA.
Collins (Contractors) Ltd v Baltic Quay Management (1994) Ltd [2004] EWCA
Negotiations and discussions were more likely to support there being a dispute than not.
Courts were likely to infer a dispute from non-admission to allow it to go to adjudication.
Comsite Projects Ltd v Andritz AG [2003]
-​Works comprised under HGCRA 105 give a right to adjudication despite which country the contract law is deemed to be.
Costain v Strathclyde Builders (2004)
-​An adjudicator's decision can be set aside if a party can demonstrate the 'mere possibility of unfairness'.

-​Parties must be given the chance to see and comment on all relevant information.

- If adjudicators own knowledge is used, parties must be told and have an opportunity to comment.
Cubitt Building & Interiors Ltd v Fleetglade Ltd [2006]
-​A decision later than the middle of the day after the deadline would not be 'forthwith' under JCT cl 41A.

-​A late referral due to late ANB appointment would not invalidate the adjudicator's appointment/jurisdiction.
Fastrack v Morrison Construction Ltd & Anor [2000]
-​If the Scheme applies, a widely written referral notice can decide the whole dispute.

-​If contract complies with the Act then perfectly permissible for it to provide for the referral of more than one dispute in the same referral.

- An adjudicator should enquire into his own jurisdiction if challenged.
Fiona Trust and Holding Corp v Privalov [2007] EWCA
-​The phrases 'arising out of', 'arising under' and 'in connection with' the contract may have the same weight of meaning.
Haden Young Ltd v Laing O'Rourke Midlands Ltd [2008]
-​Insufficient evidence of written acceptance to form a (sub-)contract. Courts agreed that payment for works done is to be valued on a 'Quantum Meruit' basis.
Hart Investments Ltd v Fidler (2006)
-​Referral outside the 7 days under the Scheme will not give jurisdiction.

-​All the terms of a contract must be in writing for the adjudication provisions of the Scheme to apply.
HG Construction Ltd v Ashwell Homes (East Anglia) Ltd (2007)
-​The courts refused to enforce an adjudication that was the same or substantially the same as a previous one.
Hills Electrical & Mechanical Plc v Dawn Construction Ltd [2004]
-​If some contractual adjudication payment provisions fail to comply with the Act then those that do not comply with the Scheme apply instead.
Holt Insulation Ltd v Colt International Ltd (2001)
-​Question answered was no, the amount (£50K) was not due. 2nd adjudication asked for 'or other such sums as the adjudicator may decide' and was deemed a different adjudication dispute by the courts.
IDE Contracting Ltd v RG Carter Cambridge Ltd (2004)
-​The notice of adjudication has to be issued to the other party before a request concerning the availability of a named adjudicator can be made or the adjudicator may not have jurisdiction.

- An indication that a named adjudicator cannot accept appointment needs to be communicated to all parties prior to making a new appointment or contacting an ANB.
John Mowlem Ltd v Hydra-Tight Ltd [2002]
-​If some contractual adjudication provisions fail to comply with the Act then all fail and the Scheme applies.

- 'Notification of dissatisfaction', under NEC contract, that delayed a referral by several weeks was not compliant with the Act. Parties have a right to adjudicate at any time.
Macob Civil Engineering Ltd v Morrison Construction Ltd [1999]
-​The proper procedure for enforcing an adjudicator's decision is by application to the TCC for summary judgement under part 24 of the Civil Procedure Rules.

-​An adjudication decision is binding and enforceable, until set aside or reversed by arbitration or litigation.

-​Adjudicator has right to determine if the Scheme is applicable.
Northern Developments (Cumbria) Ltd v J&J Nichol [2000] BLR
HHJ Bowsher QC concluded that under the Scheme an adjudicator cannot award costs. However, express clauses can allow for this.

Implied clauses were given as each party requested their costs to be awarded.
Pinochet v Amnesty International
-​Perceived bias of party's wife working for other party.
RG Carter v Edmund Nuttall Ltd (2000)
-​An application for an injunction to stay adjudication proceedings on the basis of lack of jurisdiction is not likely to succeed.
CIB Properties v. Birse Construction (2004)
Adjudicator should resign if he has insufficient time to make a fair decision.
Quietfield Ltd. v. Vascroft Contractors Ltd (2006)
Similar disputes made on different grounds or to different operational stages will be considered different and not binding on later decisions.
RJT Consulting Engineers Ltd v DM (Northern Ireland) Ltd
-​All main terms of the contract must be evidenced in writing.
RSL (South West) Ltd v Stansell Ltd
-​All parties must be given the opportunity to read and comment on any technical advice used in making a decision.
Rupert Morgan Building Services (LLC) Ltd v Jervis (2003)
-​The architects certificate determines the sums due, not the actual work done. In the absence of a s111(1) withholding notice the payment is due.
Samuel Thomas Construction Ltd v J & B Developments (Bick and Bick)
-​ Only part of a residential development was to be occupied by the developer and so the exception in HGCRA 106(1)(a) did not apply and there was a right to adjudication.
Sindall v Soland and others [2001]
-​Whether a dispute had arisen before the adjudication notice.

-​A dispute existed when 'it was clear that a point had emerged from the process of discussion or negotiation that has ended and that there is something that needs to be decided'.
Mott MacDonald Ltd v London & Regional Properties Ltd.
- Decision must be delivered as soon as possible after the decision is made.
Pring & St Hill Ltd v. CJ Hafner t/a Southern Erectors [2002] EWHC 1775 (TCC)
Decision overturned due to unfairness and thus perceived bias.

Adjudicator proceeded without express consent of the other parties for multiple disputes.
Sir Alexander Morrison v AWG Group Ltd [2006] EWCA
Judge should have withdrawn from the case due to a real possibility of perceived bais rather than actual bias or personal interest, as he had known one of the witnesses to be called.
Orange EBS Ltd v. ABB Ltd (2003)
Failure to deal with a claim within one month constituted a dispute in those circumstances.
Fileturn Ltd v. Royal Garden Hotel Ltd
Mr Sliwinski working as a company director 6 years previously in adjudication did not constitute bias.
SL Timber Systems Ltd v Carillion Construction Ltd [2001]
-​Payment claim must be substantiated for a withholding notice to be required.
Westfields Construction Ltd v Clive Lewis [2013] EWHC TCC
Court 'preferred' independant witness statements.
s106 requires ongoing residential occupation for the exception to be valid.
Whyte and Mackay Ltd v Blyth & Blyth Consulting Engineers Ltd [2013] CSOH
Some highly complex and not speed dependant cases may be inappropriate for adjudication. Courts refused to sever part of the decision even though acknowledging a certain unfairness.
William Verry Ltd v North West London Communal Mikvah [2004]
-​1 day late for the referral was not felt to be fatal to the adjudication as it was procedural not mandatory.

- An adjudicator should resign if there is insifficient time to make a fair decision.
Yarm Road Ltd v Costain Ltd (2001)
A novated contract is classed as a new contract. This made it under the new Act.
Yuanda (UK) Co Ltd v WW Gear Construction Ltd [2010]
-​If some contractual adjudication provisions fail to comply with the Act then all fail and the Scheme applies.

-​Effectively does away with Tolent clauses as being not compliant with the Act, now expressly dealt with under the revised Act`.

-​If there are written adjudication clauses in the agreement that comply with the Act then this will give jurisdiction even with residential disputes or excluded construction operations

-​As the contract interest rate was 0.5% above base it was successfully argued that this was not a substantial remedy under s8(1) of the Act and so should be replaced with the current rate of the Act of 8% above base.