How many points credits EA C1 Enhanced Commissioning have. |
Total of 6 points from two options: - Opt 1: Enhanced systems Cx - 3 to 4 pts. and/or - Opt 2: Envelope Cx - 2 pts |
|
Does Credit EA C1 award points for exemplary performance? |
No |
|
What is the Difference of EA P1 CxA and C1 CxA? |
For credit E&A C1 the CxA cannot be part of either design or construction firm nor a subcontractor to the construction firm. |
|
Requirements for EA C1 Enhanced Cx? |
In addition to the Fundamental Cx following are extra steps: - Review Submittals - Train Operations Team - 10 month Post-occupancy visit |
|
EA C1 Enhanced Cx Option 1 has how many paths? |
Path 1: Enhanced Cx - 3 pts Path 2: Enhanced & Monitoring-based Cx - 1 pt MBCx requires Path 1 achieved first. *Path 1 is one stop process while Path 2 is ongoing. |
|
What is MBCx? |
Monitoring Based Cx - is integration of following: - Permanent Energy monitoring. - Real-time Energy Analysis. - Ongoing cx. |
|
What requires to be added in Cx plan for continous monitoring? |
1- Role & Responsibilities. 2- Measurement Requirements. 3- Frequency & Duration trend monitoring. 4- Acceptable limits. 5- Performance Evaluation criteria. 6- Corrective Action Plan. 7- Training. 8- Repair & Maintenance Plan. |
|
What is option 2 Envelope Cx? |
Building Envelope Cx process is to validate that design and performance of the materials, components, assemblies and systems acheive the objectives and requirements of the owner. |
|
When BECx process starts and end? |
Begins during pre-design phase and continue for the life of the facility through the occupancy and operations phase. |