• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/3

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

3 Cards in this Set

  • Front
  • Back

If direct cost are $37000 and overhead is 12% and profit is 5% what is the selling price?

$44,578.31 (((37000 divided by 83%.... 12%+5%= 17% 100%-17%=83%

After your bid for a public-works job has been accepted by the awarding authority, you recognize that you incorrectly listed one of your subcontractors. To correct your error, what you should do?

Notify the awarding authority and request permission to make the necessary changes due your clerical error

If a general contractor fails to pay a subcontractor and the general files for bankruptcy:

The sub would probably be awarded a portion of his claim