Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
18 Cards in this Set
- Front
- Back
Free Float =
|
FF = ES(s) - EF
Free float for an activity = Early start (of successor) - early finish (of this activity) |
|
Total Float =
|
Total float = Late finish - early finish
The maximum delay before that activity delays the project |
|
Critical path =
|
Critical path = The path with the least flexibility
The path with zero or negative float The longest path "The long pole in the tent" |
|
Parametric estimating formula
|
Estimate = ((Quantity of work) x (Production rate) x (Productivity factor) x (reserve estimate)
Estimate = (600 x 1day/100) = 6 days Adjusted estimate = (6 days) x (1.5) x (1.1) = 10 days |
|
Different types of estimating are
|
Analogous estimating
Parametric estimating Bottom up estimating Three point estimating |
|
Earned Value
|
Earned Value = The budgeted value of a completed component or activity
|
|
Planned Value
|
Planned value = The budget assigned to a WBS component or activity
|
|
Actual Costs
|
Actual Costs = The costs incurred while working on or completing a component
|
|
Cost variance =
|
Cost Variance = EV - AC
Positive = under budget Negative = Over budget |
|
CPI
|
CPI = EV/AC
Cost Performance Index = EV/AC If >1.0 under of budget <1.0 Over budget |
|
Schedule Variance
|
SV = EV-PV
Schedule variance = EV-PC Positive = ahead of schedule Negative = behind schedule |
|
Schedule Performance Index
|
SPI = EV/PV
Schedule Performance Index = EV/PV >1.0 = Ahead of schedule < 1.0 = 1 behind schedule |
|
Calculate EAC using budgeted rate of work
|
EAC = AC + BAC - EV
This assumes remaining work will happen at originally budgeted costs |
|
Calculate EAC using CPI
|
EAC = BAC/CPI
This assumes all project work happens at the current CPI |
|
Calculate EAC using bottom up ETC calculation
|
EAC = AC + ETC
|
|
Calculate EAC Using SPI and CPI
MMC have never seen a question on this |
EAC = AC + ((BAC −EV)/(CPI ∗SPI))
|
|
Calculate TCPI based on the BAC
|
TCPI = ((BAC−EV) / (BAC −AC)
|
|
Calculate TCPI based on the EAC
|
TCPI = ((BAC−EV)/(EAC−AC))
|