CV Cost Variance |
EV-AC |
|
SV Schedule Variance |
EV-PV |
|
CPI Cost Performance Indicator |
EV/AC |
|
SPI Schedule Performance Indicator |
EV/PV |
|
EAC Estimate at completion Si hubo variaciones |
AC+New ETC |
|
EAC Estimate at completion Si el presupuesto se mantiene |
AC+BAC+EV |
|
EAC Estimate at completion Si se espera que CPI se mantenga |
BAC/CPI |
|
EAC Estimate at completion Dados los actuales CPI y SPI y fecha fija |
AC+((BAC-EV)/(CPI*SPI)) |
|
TCPI To Complete Performance Index |
(BAC-EV)/(BAC-AC) |
|
TCPI To Complete Performance Indes Si hay posibilidad de desempeño diferente |
(BAC-EV)/(EAC-AC) |
|
BAC Budget at Completion Significado |
Presupuesto aprobado |
|
ETC Estimate to complete Fórmula más utilizada |
EAC-AC |
|
VAC Variance at Completion |
BAC-EAC |
|
Estimacion PERT o distribución Beta |
(P+4M+0)/6 |
|
Desviación Estandar |
(P-O)/6 |
|
ETC Estimate to Complete Significado |
Monto de dinero que se estima hace falta para finalizar el proyecto. Presupuesto no gastado dado el desempeño actual |
|
ETC Estimate to complete Con varianza de costos por riesgo materializado |
(BAC-EV)/CPI |
|
Nro de Canales |
(NX(N-1))/2 |
|
VPN |
(Flujo$/(1+tasa)^periodos) |
|
PV Planned Value Significado |
Costo presupuestado |
|
EV Earned Value Significado |
Trabajo completado y aceptado en términos de costo presupuestado |
|
AC Actual Cost Significado |
Lo que realmente nos hemos gastado |
|
ETC Estimate to complete Cuando los estimados originales se mantienen |
BAC-EV |
|
ETC Estimate to complete Ascendente, BAC está errado, se debe reestimar |
(AC-BAC)+(BAC-EV) |