What are the inputs of Direct and Manage Project Execution?
|
1. Project Management Plan
2. Approved Corrective Actions 3. Approved Preventive actions 4. Approved change requests 5. Approved defect repair 6. Validated defect repair 7. Adminstrative closure procedure |
|
What are the tools and techniques for Direct and Manage Project Execution?
|
1. Project Management Methodology
2. PMIS |
|
What are the outputs of Direct and Manage Project Execution?
|
1. Deliverables
2. Requested changes 3. Implmented Change requests 4. Implemented corrective actions 5. Implemented preventive actions 6. Implemented defect repairs 7. Work Performance Information |
|
What are the inputs for acquiring the project team?
|
1. Enterprise Environmental Factors
2. Organizational process assets 3. Roles and responsibilities 4. Project organization charts 5. Staffing management plan |
|
What are the tools and techniques for acquiring the project team?
|
1. Preassignment
2. Negotiation 3. Acquisitions 4. Virtual teams |
|
What are the outputs for acquiring the project team?
|
1. Project Staff Assignment
2. Resource availability 3. Staffing management plan updates |
|
What are the inputs of Developing the project team?
|
1. Project staff assignments
2. Staffing management plan 3. Resource availability |
|
What are the tools and techniques of Developing the project team?
|
1. General Management skils
2. Training 3. Team building activities 4. Ground rules 5. Collocation 6. Recognition and rewards |
|
What are the outputs of Developing the project team?
|
Team Performance assessment
|
|
What are the inputs of Distributing Project Information?
|
Communication Management Plan
|
|
What are the tools and techniques of Distributing Project Information?
|
1. Communication skills
2. Information gathering and retrieval systems 3. Informaton distribution methods 4. Lessons learned process |
|
What are the outputs of Distributing Project Information?
|
1. Lessons learned documentation
2. Project records 3. Project reports 4. Project presentations 5. Feedback from stakeholders 6. Stakeholder notifications |
|
What are the inputs for Request Seller Responses?
|
1. Organizational process assets
2. Procurement management plan 3. Procurement documents |
|
What are the tools and techniques for Request Seller Responses?
|
1. Bidder conferences
2. Advertising 3. Develop qualified seller lists 4. |
|
What are the outputs for Request Seller Responses?
|
1. qualified sellers list
2. procurement document package 3. proposals |
|
What are the inputs for Select Sellers process?
|
1. Organizational process assets
2. Procurement management plan 3. Evaluation criteria 4. Procurement document package 5. Proposals 6. Qualified seller list 7. Project Managment Plan |
|
What are the tools and techniques for Select Sellers process?
|
1. Weighting systems
2. Independent estimates 3. Screening systems 4. Contract negotiation 5. Seller rating systems 6. Expert judgment 7. Proposal evaluation techniques |
|
What are the outputs of select sellers?
|
1. Selected sellers
2. Contract 3. Contract management plan 4. Resource availability 5. Project management plan updates 6. Requested changes |
|
What are the inputs for Quality Assurance?
|
1. Quality Managment plan
2. Quality metrics 3. Process improvement plan 4. Work performance information 5. Approved change requests 6. Quality control measurements 7. Implemented change requests 8. Implemented corrective actions 9. Implmented preventive actions 10. Implemented defect repair |
|
What are the tools and techniques for Quality Assurance?
|
1. Quality planning tools and techniques
2. Quality audits 3. Process analysis 4. Quality control tools and techniques. |
|
What are the outputs for Quality Assurance?
|
1. Requested changes
2. Recommended corrective actions 3. Organizational process assets updates 4. Project Management Plan updates |