• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/40

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

40 Cards in this Set

  • Front
  • Back
Cost management process
1. Planning: Plan Cost Management
2. Planning: Estimate Costs
3. Planning: Determine Budget
4. M&C: Control Costs
Earned value measurement
integrates cost, time, and the work done (or scope) to forecast future performance and project completion dates and costs.
PV
- Planned value
- As of today, what is estimated value of work planned to be done?
EV
- Earned value
- As of today, what is estimated value of work actually accomplished?
AC
- Actual cost (total cost)
- As of today, what is estimated value of work actually accomplished?
CPI
- Cost Performance Index
EV/AC
> 1 is good
"we are getting $ ___ worth of work for every $1 spent"
SPI
- Schedule Performance Index
EV/PV
> 1 is good
"we are progressing at __% of the rate originally planned"
BAC
- Budget at Completion (the budget)
- "How much did we BUDGET for the TOTALproject effort?"
EAC
Estimate at completion
"What do we currently expect the TOTAL project to cost (a forecast)?"
several formulas:
1. AC + Bottom-up ETC [used when original estimate was flawed]
2. BAC/CPIcum [used if continue at same rate of spending]
3. AC + (BAC - EV) [used if current variances won't be what is in the future]
4. AC + (BAC - EV) / (CPIcum x SPIcum) [used if current variances won't be what is in the future AND project schedule constraints will influence the completion of the remaining effort; i.e. when a project with a cumulative CPI <1 and a firm completion date must be met]
ETC
Estimate to complete
"From this point on, how much MORE do we expect it to cost to finish the project (a forecast)?"
VAC
Variance at completion
"As of today how much over or under budget do we expect tobe at the end of the project?"
CV
Cost Variance
EV - AC
- negative is over budget, positive is under budget
SV
Schedule Variance
EV - PV
- negative is behind schedule, positive is ahead of schedule
TCPI
To-Complete Performance Index
(BAC - EV)/ (BAC - AC)
"In order to stay within budget, what rate must we meet for the remaining work?"
- greater than 1 is bad, less than 1 is good
Cost baseline
- includes contingency reserves
- represents the funds the project manager has authority to manage and control
Cost budget
- cost baseline + management reserves
- how much money the company should have available for the project
Performance measurement baseline
3 baselines (EVM):
1. scope baseline
2. schedule baseline
3. cost baseline
Three-point estimating
pessimistic, most likely, and opmistic cost
Analogous estimating
- estimate costs based on past history
Bottom-up estimating
- create detailed estimates for each part of an activity or work package and roll up
Parametric estimating
estimating cost based on formulas and histograms
Inputs to estimating costs
1. The cost management plan - documents methods used to estimate cost & level of accuracy required for estimates
2. The scope baseline - knowing what is out o scope and what constraints have been placed on the project
3. Project schedule - includes the activities, resources, and information needed to complete the work
4. Human resource management plan - lists the human resources and associated costs to be used for the project
5. Risk register - risks have associated costs
6. Organizational process assets
9. Enterprise environmental factors
10. Project management costs
Cost management plan
- output of Plan Cost Management
- same as "budget management plan" or "budget plan"
- requires thinking ahead about how to control costs
Rough order of magnitude (ROM) estimate
- Estimate is -25% to 75% from actual
- made during project initiating
Definitive estimate
+/- 10% from actual (some do -5 to +10% from actual)
- as project progresses and estimates can be more refined
Budget estimate
-10% to +25% from actual
- during project planning
Reserve analysis
- identify which activities on the project have significant risks and determining how much time and money to set aside to account for the risks if they occur.
- Contingency & Management reserves
Contingency reserves
- money set aside for known risks
Management reserves
- lump sum used to accommodate unknown/unidentified risks
Cost risk
- Cost Management concept
- Cost-related risk
- Seller has cost risk in a fixed-price contract
Variable/fixed costs
- Type of cost
- Variable: changes with the amount of production or the amount of work (cost of material, supplies, and wages)
- Fixed: does not change as production changes (cost of set-up, rent, utilities, etc.)
Direct/indirect costs
- Type of cost
- Direct: directly attributable to the work on the project (team travel, team wages, recognition, costs of material used on the project, training for the project, etc.)
- Indirect: overhead items or costs incurred for the benefit of more than one project (taxes, fringe benefits, and janitorial services)
Life cycle costing
- Cost Management concept
- Looking at costs over the entire life of the product, not just the cost of the project to create the product
- cheaper to implement with higher annual costs or spend more to implement with cheaper annual costs
Value analysis
- Cost Management concept
- Value engineering
- "How can we decrease cost on the project while maintaining the same scope?"
Control thresholds
What amount of variation between planned and actual costs will require action
Progress reporting
- PM can monitor completion of work packages as a way to show progress on deliverables within the time and cost allotted to them in the plan
Cost of quality
- Cost of work added to the project to accommodate quality efforts should be included in the project estimate
Project management software
- no such thing as 1 software package for how to manage project
- useful in this section for estimating
Return on investment (ROI)
- Analytical technique to make financing decision
- Measure the potential profitability of an investment by calculating the benefits received in relation to cost
Discounted cash flow
- Analytical technique to make financing decision
- Estimate the attractiveness of an investment by predicting how much money will be received in the future and discounting it to its current value