Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
40 Cards in this Set
- Front
- Back
Cost management process
|
1. Planning: Plan Cost Management
2. Planning: Estimate Costs 3. Planning: Determine Budget 4. M&C: Control Costs |
|
Earned value measurement
|
integrates cost, time, and the work done (or scope) to forecast future performance and project completion dates and costs.
|
|
PV
|
- Planned value
- As of today, what is estimated value of work planned to be done? |
|
EV
|
- Earned value
- As of today, what is estimated value of work actually accomplished? |
|
AC
|
- Actual cost (total cost)
- As of today, what is estimated value of work actually accomplished? |
|
CPI
|
- Cost Performance Index
EV/AC > 1 is good "we are getting $ ___ worth of work for every $1 spent" |
|
SPI
|
- Schedule Performance Index
EV/PV > 1 is good "we are progressing at __% of the rate originally planned" |
|
BAC
|
- Budget at Completion (the budget)
- "How much did we BUDGET for the TOTALproject effort?" |
|
EAC
|
Estimate at completion
"What do we currently expect the TOTAL project to cost (a forecast)?" several formulas: 1. AC + Bottom-up ETC [used when original estimate was flawed] 2. BAC/CPIcum [used if continue at same rate of spending] 3. AC + (BAC - EV) [used if current variances won't be what is in the future] 4. AC + (BAC - EV) / (CPIcum x SPIcum) [used if current variances won't be what is in the future AND project schedule constraints will influence the completion of the remaining effort; i.e. when a project with a cumulative CPI <1 and a firm completion date must be met] |
|
ETC
|
Estimate to complete
"From this point on, how much MORE do we expect it to cost to finish the project (a forecast)?" |
|
VAC
|
Variance at completion
"As of today how much over or under budget do we expect tobe at the end of the project?" |
|
CV
|
Cost Variance
EV - AC - negative is over budget, positive is under budget |
|
SV
|
Schedule Variance
EV - PV - negative is behind schedule, positive is ahead of schedule |
|
TCPI
|
To-Complete Performance Index
(BAC - EV)/ (BAC - AC) "In order to stay within budget, what rate must we meet for the remaining work?" - greater than 1 is bad, less than 1 is good |
|
Cost baseline
|
- includes contingency reserves
- represents the funds the project manager has authority to manage and control |
|
Cost budget
|
- cost baseline + management reserves
- how much money the company should have available for the project |
|
Performance measurement baseline
|
3 baselines (EVM):
1. scope baseline 2. schedule baseline 3. cost baseline |
|
Three-point estimating
|
pessimistic, most likely, and opmistic cost
|
|
Analogous estimating
|
- estimate costs based on past history
|
|
Bottom-up estimating
|
- create detailed estimates for each part of an activity or work package and roll up
|
|
Parametric estimating
|
estimating cost based on formulas and histograms
|
|
Inputs to estimating costs
|
1. The cost management plan - documents methods used to estimate cost & level of accuracy required for estimates
2. The scope baseline - knowing what is out o scope and what constraints have been placed on the project 3. Project schedule - includes the activities, resources, and information needed to complete the work 4. Human resource management plan - lists the human resources and associated costs to be used for the project 5. Risk register - risks have associated costs 6. Organizational process assets 9. Enterprise environmental factors 10. Project management costs |
|
Cost management plan
|
- output of Plan Cost Management
- same as "budget management plan" or "budget plan" - requires thinking ahead about how to control costs |
|
Rough order of magnitude (ROM) estimate
|
- Estimate is -25% to 75% from actual
- made during project initiating |
|
Definitive estimate
|
+/- 10% from actual (some do -5 to +10% from actual)
- as project progresses and estimates can be more refined |
|
Budget estimate
|
-10% to +25% from actual
- during project planning |
|
Reserve analysis
|
- identify which activities on the project have significant risks and determining how much time and money to set aside to account for the risks if they occur.
- Contingency & Management reserves |
|
Contingency reserves
|
- money set aside for known risks
|
|
Management reserves
|
- lump sum used to accommodate unknown/unidentified risks
|
|
Cost risk
|
- Cost Management concept
- Cost-related risk - Seller has cost risk in a fixed-price contract |
|
Variable/fixed costs
|
- Type of cost
- Variable: changes with the amount of production or the amount of work (cost of material, supplies, and wages) - Fixed: does not change as production changes (cost of set-up, rent, utilities, etc.) |
|
Direct/indirect costs
|
- Type of cost
- Direct: directly attributable to the work on the project (team travel, team wages, recognition, costs of material used on the project, training for the project, etc.) - Indirect: overhead items or costs incurred for the benefit of more than one project (taxes, fringe benefits, and janitorial services) |
|
Life cycle costing
|
- Cost Management concept
- Looking at costs over the entire life of the product, not just the cost of the project to create the product - cheaper to implement with higher annual costs or spend more to implement with cheaper annual costs |
|
Value analysis
|
- Cost Management concept
- Value engineering - "How can we decrease cost on the project while maintaining the same scope?" |
|
Control thresholds
|
What amount of variation between planned and actual costs will require action
|
|
Progress reporting
|
- PM can monitor completion of work packages as a way to show progress on deliverables within the time and cost allotted to them in the plan
|
|
Cost of quality
|
- Cost of work added to the project to accommodate quality efforts should be included in the project estimate
|
|
Project management software
|
- no such thing as 1 software package for how to manage project
- useful in this section for estimating |
|
Return on investment (ROI)
|
- Analytical technique to make financing decision
- Measure the potential profitability of an investment by calculating the benefits received in relation to cost |
|
Discounted cash flow
|
- Analytical technique to make financing decision
- Estimate the attractiveness of an investment by predicting how much money will be received in the future and discounting it to its current value |