• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/53

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

53 Cards in this Set

  • Front
  • Back

What are the 6 tools and techniques for the "Control Costs" process?

1) Earned Value Management


2) Forecasting


3) To-complete performance index (TCPI)


4) Performance reviews


5) Variance analysis


6) Project management software

What are the 5 tools and techniques for the "Determine Budget Process?"

1) Cost aggregation


2) Reserve analysis


3) Expert judgement


4) Historical relationships


5) Funding limit reconciliation

What are the 2 main categories of cost in cost of quality?

1) Conformance


2) Non-conformance

What does forecasting mean?

Developing an estimate of the cost of the project, at completion, based upon project performance. This is called EAC (estimate at completion).

What are the 4 inputs to the Control Costs process?

1) Project management plan


2) Project funidng requirements


3) Work performance information


4) Organizational process assets

What are the 3 outputs of the Estimate Costs Process?

1) Activity cost estimates


2) Basis of estimates


3) Project document updates

What is parametric estimating?

A top to bottom method of estimating, using a statistical relationship between historical data and other parameters to calculate an estimated cost for activities.

What are the 3 earned value data points?

1) PV (planned value)


2) EV (earned value)


3) AC (actual cost)

What are the 4 constraints that might affect your cost estimates?

1) Limited budget


2) Required delivery dates


3) Availability of skilled resources


4) Organizational policies

What is the usual method of showing the cost baseline and expenditures?

An S-curve

What are the 7 resources for which cost estimates should be developed on a project?

1) Labor


2) Materials


3) Equipment


4) Services


5) Facilities


6) Inflation allowance


7) Contingency

What is the standard deviation formula for the PERT equation?

SD = (Cp -Co)


-----------


6

What is the EAC forecast for ETC work considering both SPI and CPI factors?

EAC = AC + [ BAC - EV ]


-------------------------------


Cum CPI x Cum SPI

What is the most accurate EAC formula that works in every project case and must be used when the original estimates are fundamentally flawed?

EAC = AC + a new bottom-up ETC

What does the term EAC mean?

Estimate at Completion

What is the TCPI (to complete performance index) formula when the original BAC is no longer achievable and the project is rebaselined to the new EAC?

TCPI = BAC - EV


------------


EAC - AC

What is the EAC forecast for a project that is expected to accomplish the ETC work at the current CPI rate?

EAC = [ BAC ]


----------------------------


cumulative CPI

What are the forumlas for SPI (schedule performance index) and CPI (cost performance index)?

SPI = EV / PV



CPI = EV / AC

What is the total planned value for a project also known as?

The BAC (budget at completion)

What is the function of the reserve analysis tool in estimate costs?

1) To establish the contingency reserv, which is an allowance for unplanned, not initially identified, but potentially required changes (know unknowns)



2) To make sure that adequate reserves remain at the project progresses.

Later in the Planning phase, what is the cost estimate called?



What is the range?

1) Definitive Estimate



2) Range = +/- 10%

Describe "Estimate at Completion (EAC)"

A forecast of how much we think the project will cost when it is finished.

Describe "Estimate to Completion (ETC)"

A forecast of how much money we expect to spend.

Which process contains the activities to approximate the monetary resources needed to complete individual activities or work packages?

The "Estimate Costs" Process.

Which process aggregates the estimated cost of individual activities or work packages to establish an authorized baseline?

The "Determine Budget" Process.

"Bottom up Estimating" is a "tool & technique" of what process?

The "Extimate Activity Resources" process.

The "cost baseline" is output of what process?

The "Determine Budget" Process.

What information does "Index Formulas" (SPI, CPI, CCPI) provide?

They give project efficiency info or how "efficiently" you are using time and / or resources.

What is the purpose of the "Control Costs" process?

It's the process of monitoring the status of the project budget and managing changes to cost baseline.

Any change to the authorized budget must be made through what process?

The "Perform Integrated Change Control" Process

Which process seeks out causes of both positive and negative variances and is part of the "Integrated Change control" process.

The "Project Cost Control" process.

What does the "Budgeted Cost of Work Scheduled (BCWS)" predict?

BCWS estimates the value of work to be completed by a project within a specific time period.

What is the formula for Planned Value (PV)?

Planned % complete * Budget at Completion (BAC)

What is the formula for Schedule Performance Index (SPI)?

EV


----


PV

What is the formula for Cost Performance Index (CPI)?

CV


----


AC

What is the formula for Cumalitive Cost Performance Index (CCPI)

Cumalative EV


--------------------


Cumalative AC

What does it mean if the Schedule Performance Index (SPI) is less than 1.0?

You are behind schedule.



Greater than 1.0, you are ahead of schedule.



SPI = EV / PV



It is the measure of progress achieved compared to progress planned on a project. The per

Define SWOT Analysis?

SWOT = Strength, Weaknesses, Oppurtunities & Threats. It is the subjective assessment of a given situation to make decisions on planning & management. Ask Questions, organize answers into a template.

Define Value Analysis?

The goal is to increase value by reducing the cost / function relationship.

Define Stakeholder Analysis?

It identifies the stakeholders of the project and determines their needs, wants and expectations.

Define Lateral Thinking?

This is a "tool and technigue" of scope definition. It means "thinking out of the box". It means to separate yourself from the problem and look at it from different angles.

Describe "Actual Costs"

Actual Costs or "Actual Cost of Work Produced" are the actual costs incurred by the project at a certain point in time. In other words, you add up all the costs incurred by the project as of today.



Actual Costs has no upper limit.

Describe "Schedule Variance"

The "schedule variance" shows whether a project is ahead or behind schedule.



SV = EV - PV


+ = good


- = bad


0 = on plan

Describe "Earned Value"

Also known as "Basic Cost of Work Produced" or BCWP. It is the estimated value of the work completed on your project as of today.



EV = Percent Complete * BAC.


Describe "Cost Performance Index" or (CPI)

CPI is the measure of the "Value" of work completed compared to the actual cost or progress made on a project.

Describe "Schedule Variance"

SV is the measure of Schedule Performance on a project



SV = EV - PV

Describe "Cost Variance"

This is the measure of Cost Performance on a project.



CV = EV - AC

Describe "Planned Value"

It is the authorized budget assigned to the work to be accomplished for an activity or a WBS component.



Sometimes total of PV is known as Performance Measurement Baseline. Also, known as Budget at Completion (BAC)

Describe "Cost Baseline"

Cost Baseline includes all authorized budgets but EXCLUDES management reserves. Management reserves are not part of EVM.



Project Cost Performance will be measured against the authorized budget.

Describe the "Taguchi Method"

`This method computes a "loss function" used to determine the cost of producing products that fail to achieve a target value.

True or False? A revised cost baseline may need to be created to provide a realistic basis for performance measurement.

True.

Describe "Direct Charges"

These are the costs allocated to a project by the project team as the cost of doing business.

Describe "Indirect Charges"

These are "overhead" or costs incurred for benefit of more than one project. It is usually a percentage of direct costs. For example, overhead lights.