Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
25 Cards in this Set
- Front
- Back
Direct Cost |
is directly attributable to the project and spent only on project work.
Example: Is the salaries of coders working on a software project. |
|
Indirect Cost |
is not directly attributable to the project, but often allocated to the project.
Example: Such a cost could be security for the building where the work of the project is performed. |
|
Fixed Cost |
consistent throughout the project lifecycle regardless of project activity. The leasing of office space for a software project is a fixed cost. |
|
Variable Cost |
is cost that fluctuates with project activity. |
|
ROI |
Return on Investment
Option to Elect: largest number or % |
|
IRR |
Internal Rate of Return
Option to elect: Largest Percentage |
|
NPR |
Net Present Value
Compares the value of a dollar today versus the value of that same dollar in the future, after taking inflation and discount rate into account.
Option to elect: Largest number ( years are already factored in) |
|
BCR |
Benefits Cost Ratio
Option: Largest Ratio
Example: 200,000 in revenue and 50,000 of cost have a BCR of 4:1. |
|
Opportunity Cost |
Is associated w/ taking another opportunity. It is what you give or leave on the table. |
|
Payback Period |
Is the amount of time needed to earn back the original investment.
|
|
Sunk Cost |
Is a cost that has already been spent on a project. Do not consider sunk cost when making project decisions.
Example: if a project has a budget of 175,000 and has already spent 200,000, you would not consider the 200,000 when deciding whether to continue on the project or not. |
|
Depreciation |
is the process of devaluing a capital asset in the tax system. Capital assets are those that are purchased and depreciated over time.
Examples: office equipment, vehicles, and technology infrastructure. |
|
Actual Cost (AC) |
Sum of Actual Costs |
|
Earned Value (EV) |
% complete of project |
|
Present Value (PV) |
Value of Scheduled Work |
|
Budget at Completion (BAC) |
Total Budget |
|
Cost Performance Index (CPI) |
EV/AC |
|
Cost Variance (CV) |
EV-AC |
|
Schedule Performance Index (SPI) |
EV/PV |
|
Schedule Variance (SV) |
EV-PV |
|
Estimate at completion (EAC) |
BAC/CPI |
|
Estimate to Complete (ETC) |
EAC-AC |
|
Variance at Completion (VAC) |
BAC-EAC |
|
To-Complete Performance Index (TCPI) |
(BAC-EV)/(BAC-AC) |
|
Life Cycle Cost or Total Cost of Ownership |
Is the process of examining all costs associated with a project and its product once it goes into production. |