• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/25

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

25 Cards in this Set

  • Front
  • Back

Direct Cost

is directly attributable to the project and spent only on project work.



Example: Is the salaries of coders working on a software project.

Indirect Cost

is not directly attributable to the project, but often allocated to the project.



Example: Such a cost could be security for the building where the work of the project is performed.

Fixed Cost

consistent throughout the project lifecycle regardless of project activity. The leasing of office space for a software project is a fixed cost.

Variable Cost

is cost that fluctuates with project activity.

ROI

Return on Investment



Option to Elect: largest number or %

IRR

Internal Rate of Return



Option to elect: Largest Percentage

NPR

Net Present Value



Compares the value of a dollar today versus the value of that same dollar in the future, after taking inflation and discount rate into account.



Option to elect: Largest number ( years are already factored in)

BCR

Benefits Cost Ratio



Option: Largest Ratio



Example:


200,000 in revenue and 50,000 of cost have a BCR of 4:1.

Opportunity Cost

Is associated w/ taking another opportunity. It is what you give or leave on the table.

Payback Period

Is the amount of time needed to earn back the original investment.


Sunk Cost

Is a cost that has already been spent on a project. Do not consider sunk cost when making project decisions.



Example: if a project has a budget of 175,000 and has already spent 200,000, you would not consider the 200,000 when deciding whether to continue on the project or not.

Depreciation

is the process of devaluing a capital asset in the tax system. Capital assets are those that are purchased and depreciated over time.



Examples: office equipment, vehicles, and technology infrastructure.

Actual Cost (AC)

Sum of Actual Costs

Earned Value (EV)

% complete of project

Present Value (PV)

Value of Scheduled Work

Budget at Completion (BAC)

Total Budget

Cost Performance Index (CPI)

EV/AC

Cost Variance (CV)

EV-AC

Schedule Performance Index (SPI)

EV/PV

Schedule Variance (SV)

EV-PV

Estimate at completion (EAC)

BAC/CPI

Estimate to Complete (ETC)

EAC-AC

Variance at Completion (VAC)

BAC-EAC

To-Complete Performance Index (TCPI)

(BAC-EV)/(BAC-AC)

Life Cycle Cost or Total Cost of Ownership

Is the process of examining all costs associated with a project and its product once it goes into production.