• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/35

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

35 Cards in this Set

  • Front
  • Back

Is prequalification of bidders legal on public projects

Yes

What governs between supplementary and general conditions

Supplementary conditions

Is a surety bond like an insurance policy?

No

A common time for the owner to review the preliminary design is when about ____% of the total design is complete

40

List the four major construction industry segments

building, industrial, residential, heavy/highway

What is the percentage of the bid price incurred by the constructor for cost estimating

0.25%

Provide changes or additions to the contract documents after they have been issued but before the bids are due

Addendum

Cover stipulations, regarding how a contract is to be administered and the relationships between the parties involved that are the same for all contracts

General conditions

Provide technical information that is best conveyed by graphic or pictorial representations

Plans and drawings

Supplied by the owner and used by the contractor to submit its bid

Proposal form

Present those aspects of the contractual relationships that are peculiar or unique to a given project

supplementary conditions

Provide technical information that is best conveyed by verbal descriptions

Technical specifications

Example of a project indirect cost

Salary of the project manager

Index which tracks the cost of typical materials used in residential construction projects

Input cost index

Index tracks the cost of completed homes over time and around the country

Output cost index

Performance bonds are what percent of project costs

0.5-3%

When a facility can be occupied for its intended use

Beneficial occupancy

Change to the contract that is issued unilaterally by the owner

Change order

Relates to determining how construction resources can best be applied

Construction management

Methods or techniques used to place the materials and elements of construction at the job site

Construction technology

Written notification from the owner to the constructor that the constructor has received the contract

Notice to proceed

Deficiencies identified during the final inspection

Punch List

Four categories of direct cost

Labor, equipment, materials, subcontracts

Two types of industry

Service and construction

Three parties in the surety contract

Obligee (owner) , principal (constructor), surety

What 3 items are included in the contractor's "markup"

profit, contingency, home/office overhead

What are the two primary purposes of the final owner's estimate

Provides a basis against which the owner can compare contractor bids


Lets owner know if the final design is within the owner's financial resources to construct

Three production systems and their production volumes

Project (low), Batch system (medium), mass-production (high)

Which production system is most applicable to the construction industry

Project

Claims for time extensions are typically for the 2 general reasons

Weather problems, acts of the owner or its agents

Four methods of specifying construction products

Proprietary, descriptive, Process

What do owners often require to guard against mechanics liens

Payment bonds

Requires that on federal projects the contractor must provide surety bonds

Miller act of 1935

In a construction contract, what is the difference between a change and a cardinal change

A cardinal change is no longer within the scope of the project and is therefore considered a new contract. A change is typically within the scope and only requires additional compensation for the contractor

Which type of cost+ contract actually encourages the contractor to increase construction cost

Cost +% of cost