43 Cards in this Set

  • Front
  • Back
What is the definition of Integration in the context of making a project?
Integration: is making choices about where to concentrate resources and effort on any given day, anticipating potential issues, dealing with these issues before they become critical, and coordinating work for the overall project good.
What does the integrative project management processes include?
4.1 Develop Project Charter
4.2 Develop Preliminary Project Scope Statement
4.3 Develop Project Management Plan
4.4 Direct and Manage Project Execution
4.5 Monitor and Control Project Work
4.6 Integrated Change Control
4.7 Close Project
What is a Project Charter?
The project charter is the document that formally authorize a project.
What is developing the project charter primarily concerned with?
Documenting the business needs, project justification, current understanding of the customers requirements, and the new product, service or result that is intended to satisfy those requirements
What are the Project Charter Inputs?
.1 Contract (When Applicable)
.2 Project Statement of Work
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
What is the definition of Statement of Work?
the statement of work (SOW) is a narrative description of products or services to be supplied by the project
What are the Tools and Techniques used to Develop the Project Charter?
.1 Project Selection Methods
.2 Project Management Methodology
.3 Project Management Information System
.4 Expert Judgement
What are Project Selection Methods used for?
Project Selection Methods are used to determine which project the organization will select.
(Develop Project Charter: Tools and Techniques)
What is Project Management Methodology?
Project management methodology defines a set of Project Management Process Groups, their related processes and the related control functions that are consolidated and combined into a functional unified whole.
(Develop Project Charter: Tools and Techniques)
What is a Project Management Information System?
The Project Management Information System (PMIS) is a standardized set of automated tools available within the organization and integrated into a system.
(Develop Project Charter: Tools and Techniques)
When is Expert Judgment used?
Expert judgment is often used to access the inputs needed to develop the project charter.
(Develop Project Charter: Tools and Techniques)
What is the Output for Develop Project Charter?
.1 Project Charter
What are the Inputs for the Development of the Preliminary Project Scope Statement?
.1 Project Charter
.2 Project Statement of Work
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
What are the Tools and Techniques used in the Development of the the Preliminary Project Scope Statement?
1 Project Management Methodology
.2 Project Management Information System
.3 Expert Judgment
What is the Output of the Development of the Preliminary Project Scope Statement?
.1 Preliminary Project Scope Statement
What does the Develop Project Management Plan Process include?
The Develop Project Management Plan process includes the actions necessary to define, integrate, and coordinate all the subsidiary plans into a project management plan.
What is the Project Management Plan?
The Project Management Plan defines how the project is executed, monitored and controlled, and closed.
What are the Inputs for the Development of the Project Management Plan?
.1 Preliminary Project Scope Statement
.2 Project Management Processes
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
What are the Tools and Techniques used in the Development of the Project Management Plan?
.1 Project Management Methodology
.2 Project Management
Configuration Management System
Change Control System
.3 Expert Judgment
What is the Output for the Development of the Project Management Plan?
.1 Project Management Plan
What does the Direct and Manage Project Execution process require?
The Direct and Manage Project Execution process requires that the project manger and the project team to perform multiple actions to execute the project management plan to accomplish the work defined in the project scope statement.
What are the Inputs in the Direct and Management Project Execution Process?
.1 Project Management Plan
.2 Approved Corrective Actions
.3 Approved Preventative Actions
.4 Approved Change Requests
.5 Approved Defect Repair
.6 Validated Defect Repair
.7 Administrative Closure Procedure
What are Approved Corrective Actions?
Approved Corrective actions are documented, authorized directions required to bring expected future project performance into conformance with the project management plan
(Direct and Manage Project Execution: Inputs)
What are Approved Preventative Actions?
Approved preventive actions are the documented, authorized directions that reduce the probability of negative consequences associated with the project risks.
(Direct and Manage Project Execution: Inputs)
What are Approved Change Requests?
Approved change requests are the documents, authorized changes to expand or contract project scope.
(Direct and Manage Project Execution: Inputs)
What is the Approved Defect Repair?
The approved defect repair is the documented, authorized request for product correction of a defect found during the quality inspection or the audit process.
(Direct and Manage Project Execution: Inputs)
What is the Validated Defect Repair?
Notification that re-inspected repaired items have been either accepted or rejected.
(Direct and Manage Project Execution: Inputs)
What is the Administrative Closure Procedure?
The administrative closure procedure documents all the activities, interactions, and related roles and responsibilities needed in executing the administrative closure procedure for the project.
(Direct and Manage Project Execution: Inputs)
What are the Tools and Techniques used in the Direct and Manage Project Execution Process?
.1 Project Management Methodology
.2 Project Management Information System
What are the Outputs for the Direct and Manage Project Execution Process?
.1 Deliverables
.2 Requested Changes
.3 Implemented Change Requests
.4 Implemented Corrective Actions
.5 Implemented Preventive Actions
.6 Implemented Defect Repair
.7 Work Performance Information
What is a Deliverable?
A deliverable is any unique and verifiable product, result or capability to perform a service that is identified in the project management planning documentation, and must be produced and provided to complete the project.
(Direct and Mange Project Execution: Outputs)
What are Requested Changes?
Changes requested to expand or reduce project scope, to modify policies or procedures, to modify project cost budget, or to revise the project schedule are often identified while the project work is being performed.
(Direct and Mange Project Execution: Outputs)
What are Implemented Change Requests?
Approved change requests that have been implemented by the project management team during project execution.
(Direct and Mange Project Execution: Outputs)
What are Implemented Corrective Actions?
The approved corrective actions that have been implements by the project management team to bring expected future project performance into conformance with the project management plan.
(Direct and Mange Project Execution: Outputs)
What are Implemented Preventive Actions?
The approved preventive actions have been implemented by the project management team to reduce the consequences of the project risks.
(Direct and Mange Project Execution: Outputs)
What is Implemented Defect Repair?
During project execution, the project management team has implemented approved product defect corrections.
(Direct and Mange Project Execution: Outputs)
What is Work Performance Information?
Information of the status of the project activities being performed to accomplish the project work is routinely collected as part of the project management plan execution.
(Direct and Mange Project Execution: Outputs)
Why is the Monitor and Control Project Work Process performed?
The monitor and control project work process is performed to monitor project processes associated with initiating, planning, executing, and closing.
What is Monitoring?
Monitoring includes collecting, measuring, and disseminating performance information, and assessing measurements and trends to effect process improvements.
What are the Inputs in the Monitor and Control Project Work Process?
.1 Project management Plan
.2 Work Performance Information
.3 Rejected Change Requests
What are the Tools and Techniques used in the Monitor and Change Project Work Process?
.1 Project Management Methodology
.2 Project Management Information System
.3 Earned Value Technique
.4 Expert Judgment
What is the Earned Value Technique?
The earned value technique measures performance of the project as it moves from project initiation through project closure.
(Monitor and Change Project Work: Tools and Techniques)
What are the Outputs of the Monitor and Change Project Work Process?
.1 Recommended Corrective Actions
.2 Recommended Preventive Actions
.3 Forecasts
.4 Recommended Defect Repair
.5 Requested Changes