• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/42

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

42 Cards in this Set

  • Front
  • Back
ctual Cost (AC)
The actual amount of monies the project has spent to date.
Analogous Estimating
An approach that telies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.
Botton-Up Estimating
An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the ost tiem-consuming and most reliable methods to predict project costs.
Budget Estimate
This estimate is also somewhat broad and is used early in the planning processes and also is top-down estimates. The range of variance for the estimate can be from - 10 percent to +25 percent.
Commercial Database
A cost-estimating approach that uses a database, typically software driven, to create the cost estimate for a project.
Contingency Reserve
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager's discretion and with management's approval to counteract cost overruns for scheduled activities.
Cost Aggregation
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
Cost Baseline
A time-lapse exposure of when the project mon ies are to be spent in relation to comulative values of the work completed in the project.
Cost Budgeting
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
Cost Change Control System
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
Cost Managment Plan
The cost managment plan dictates how cost variances will be managed.
Cost of Poor Quality
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.
Cost of Quality
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
Cost Performance Indes (CPI)
Measures the project bases on its financial performance. The formula is CPI = EV/AC.
Cost Variance (CV)
The difference of the earned value amount and the cumulative actual costs of the project. The formula is CV = EV - AC.
Definitive estimate
This estimate type is one of the most accurate. It's used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from -5 percent to +10 percent.
Direct Costs
Costs are attributed directly to the project work and cannot be shared among projects. (for example, airfare, hotels, long-distance phone charges, and so on).
Earned Value (EV)
Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
Estimate At Completion (EAC)
These forcasting formulas predict the likely completed costs of the project based on current scenarios within the project.
Estimate To C omplete (ETC)
An earned value managment formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.
Fixed Costs
Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on tot he project, and so on).
Funding Limit Reconciliation
An organization's approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints.
Indirect Costs
Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project managment software license, and so on).
Known Unknown
An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk related.
Learning Curve
An approach that assumens the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.
Oligoploly
A market conditionwhere the market is so tight that the actions of one vendor affect the actions of all the other.
Opportunity Cost
The total cost of the opportunity that is refused to realize an opposing opportunity.
Parametic Estimating
An approach using a parametric model to extrapolate what costs will be for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.
Planned Value (PV)
Planned value is the work sceduled and the budge authorized to accomplish the work. It is the percentage of the BAC that reflects where the project whould be at this point in time.
Project Variance
The final variance, which is discovered only at the project's completion. The formula is VAR = BAC - AC.
Regression Analysis
This is a statistical approach to predicting what future values may be, based on historical values. Regression analysis creates quantitiative predictions based on variables wthin one value to predict variables in another. This form of estimating relies solely on pure statistical math to reveal relationships between variables and to predict future values.
Reserve Analysis
Cost reserves are for unknown unknowns withinin a project. The contingency reserve is not part of the project cost baseline, but is included as part of the project budget.
Rough Order of Magnitude
This rough estimate is used during the initiating processes and in top-down estimates. The reange of variance for the estimate can be from -25 percent to +75 percent.
Schedule Performance Index (SPI)
Measures the project based on its schedule performance. The formula is SPI = EV/PV.
Schedule Variance (SV)
The differnece between the earned value and the planned value. The formula is SV = EV - PV.
Single Source
Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.
Sole Source
Only one vendor can proveide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.
Sunk Costs
Monies that have already been invested in a project.
To-Complete Performance Index
A formula to forecast the likelihood of a project ot achieve its goals based on what's happening in the project right now. There are two differenct flavors for the TCPI, depending on what you want to accomplish. If you want to see if your project can meet the budget at completion, you'll use this formula: TCPI = (BAC - EV)/(BAC - AC). If you want to see if your project can meet the newly created estimate at completion, you'll use this version of the formula: TCPI = (BAC - EV)/(EAC - AC).
Variable Costs
Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).
Variance
The difference between what was expected and what was experienced.
Variance At Completion (VAC)
A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is VAC = BAC - EAC.