Initiating Integration Management |
Develop Project Charter |
|
Develop Project Charter inputs |
SOW Business case Agreement Enterprise environmental factors Organizational process assets |
|
Develop Project charter tools |
Expert judgment Facilitation techniques |
|
Develop Project charter output |
Project charter |
|
Planning integration management |
Project management plan |
|
Project management plan input |
Project charter Output from other processes Enterprise environmental factors Organizational process assets |
|
Project management plan tool |
Expert judgement Facilitation techniques |
|
Project management plan output |
Project management plan |
|
Executing integration management |
Direct and manage project work |
|
Direct and manage project work input |
Project management plan Approved change requests Enterprise environmental factors Organizational process assets |
|
Direct and manage project work tools |
Expert judgment Project management information system Meetings |
|
Direct and manage project work output |
Deliverables Work performance data Change Requests Project management plan updates Project document updates |
|
Monitor and control integration |
Monitor and control project work and Perform integrated change control |
|
Monitor and control project work input |
Project mgmt plan Schedule forecast Cost forecast Validate changes Work performance information Enterprise environmental factors Organizational process assets |
|
Monitor and control project work tool |
Expert judgement Analytical techniques Project management information system (pmis) Meeting |
|
Monitor and control project work output |
Change request Work performance reports Project management plan updates Project document updates |
|
Perform integrated change control input |
Project management plan Work performance reports Change requests Enterprise environmental factors Organizational process assets |
|
Change VS configuration control |
Configuration control deals with attributes or parameters of product and change deals with change request |
|
Configuration management activities in perform integrated change control |
Identify, confirm status, and verify completion |
|
Perform integrated change control tools |
Expert judgement Meeting Change control tools |
|
Perform integrated change control output |
Approved change requests Change log Project plan updates Project docs updates |
|
Close integration |
Close project or phase |
|
Close project or phase input |
Project plan Accepted deliverables Organizational process assets |
|
Close project or phase tools |
Expert judgement Meetings Change control tools |
|
Close project or phase outputs |
Final product, service, or result transition Organizational process assets updates |
|
Planning scope management |
Plan scope management Collect requirements Define scope Create wbs |
|
Plan scope management input |
Project plan Project charter Enterprise environmental factor Organizational process assets |
|
Plan scope management tools |
Expert judgement Meetings |
|
Plan scope management output |
Scope management plan Requirements management plan |
|
Collect requirements input |
Scope management plan Requirements management plan Stakeholder management plan Project charter Stakeholder register |
|
Collect requirements tools |
Interviews Focus groups Facilitated workshops Group creativity techniques techniques InterviewsFocus groupsFacilitated workshopsGroup creativity techniquesGroup decision making techniquesQuestionnaires and surveysObservationsPrototypesBenchmarkingContext diagramsDocument analysis Questionnaires and surveys Group decision making techniquesQuestionnaires and surveysObservationsPrototypesBenchmarkingContext diagramsDocument analysis Observations Prototypes Benchmarking Context diagrams Document analysis |
|
Collect requirements outputs |
Requirements documentation Requirements traceability matrix |
|
Define scope input |
Scope management plan Project charter Requirements documentation Organizational process assets |
|
Define scope tools |
Expert judgement Product analysis Alternatives generation Facilitated workshops |
|
Define scope output |
Project scope statement Project documents updates |
|
What is included in the scope statement |
Project goals Project description Deliverables including status reports Constraints and assumptions Risks Cost estimates Acceptance criteria Project exclusions |