• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/3

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

3 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
Liquidated damages are contractual clauses that call for
an amount to be paid if the contractor does not finish the job on time
The difference between a bar chart schedule and a Critical Path Method schedule (CPM) is that the CPM includes
the relationship of the various activities to each other
A builder is expecting the final payment for 4 jobs. All amounts billed have been paid except for the final billing and the retainage. Each job has had 10% retainage withheld on the amounts paid. The total contract amounts and the final billing for each job are shown below.
Contract Amount Final Billing
Job a $6,300 $1,500
Job b $8,750 $1,520
Job c $9,800 $1,900
Job d $13,680 $2,660
What is the total amount the builder should receive for all of the final payments due?
between $9,001 and $12,000
(6300+8750+9800+13680)×10%=3853 so 3853+1500+1520+1900+2660=11433