Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
32 Cards in this Set
- Front
- Back
What is the process of time management? |
Plan Schedule Management |
|
What is the key output of the Plan Schedule Management process? |
Schedule management plan |
|
What are the key outputs of the Define Activities process? |
Activity list
|
|
What are the key outputs of the Sequence Activities process? |
Network diagrams
|
|
What are some of the key outputs of the |
Activity resource requirements
|
|
What are the key outputs of the Estimate Activity Durations process? |
Activity duration estimates
|
|
What does the Develop Schedule process involve?
|
Creating a project schedule that is bought into, approved, realistic, and formal
|
|
What are the key outputs of the Control Schedule process? |
Work performance information
|
|
What are the four types of logical relationships between activities in the precedence diagramming method? |
Finish-to-start (FS): An activity must finish before the successor can start
|
|
What are mandatory dependencies?
|
Mandatory: The order in which activities MUST be done, due to the
|
|
What are external dependencies?
|
External: Dependencies based on the needs of a party OUTSIDE the project
|
|
What is a lag?
|
Lag: Waiting time inserted between activities
|
|
What is a resource breakdown structure? |
An organizational chart or table showing identified resources, organized by category and type |
|
How does a schedule model differ from a schedule? |
The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.
|
|
What is the critical path?
|
Critical: The longest path through the network diagram
|
|
How does the critical path help us manage the project? |
It shows the project manager the shortest time in which the project can be completed
|
|
Define total float, free float, and project float |
Total float: The amount of time an activity can be delayed without delaying the project end date or an intermediary milestone
|
|
What are the two formulas for calculating float? |
Late start - Early start |
|
What are the methods that can be used to compress a schedule? |
Crashing
|
|
What is crashing? |
Adding or adjusting resources in order to compress the schedule while maintaining the original project scope |
|
What is fast tracking? |
Compressing the schedule by doing more critical path activities in parallel |
|
What is the critical chain method? |
A schedule network analysis tool that builds in buffers at critical milestones |
|
What is reestimating? |
Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot |
|
What is resource optimization? |
Finding ways to adjust the use of resources |
|
What is resource leveling? |
A resource optimization technique that keeps the amount of resources used for each time period constant, resulting in a more stable level of resources and a longer project duration |
|
What is resource smoothing? |
A modified form of resource leveling, where resources are leveled only within the limits of the float of their activities, so the completion dates of activities are not delayed |
|
What is the schedule baseline? |
The approved version of the schedule model, along with any approved changes, used to measure project schedule performance |
|
What are the main presentation formats for a schedule? |
Network diagrams |
|
What do network diagrams show? |
Dependencies (logical relationships) between activities
|
|
What do simple bar charts show? |
Project schedule or project status |
|
What do milestone charts show? |
High-level project status |
|
What is Monte Carlo analysis? |
A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific cost
|