• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/32

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

32 Cards in this Set

  • Front
  • Back

What is the process of time management?

Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule

What is the key output of the Plan Schedule Management process?

Schedule management plan

What are the key outputs of the Define Activities process?

Activity list



Activity attributes



Milestone list

What are the key outputs of the Sequence Activities process?

Network diagrams



Updates to project documents

What are some of the key outputs of the
Estimate Activity Resources process?

Activity resource requirements



Resource breakdown structure

What are the key outputs of the Estimate Activity Durations process?

Activity duration estimates



Updates to project documents

What does the Develop Schedule process involve?



What are some of its key outputs?

Creating a project schedule that is bought into, approved, realistic, and formal



Project schedule
Schedule baseline
Updates to the project management plan and project documents

What are the key outputs of the Control Schedule process?

Work performance information



Schedule forecasts



Change requests

What are the four types of logical relationships between activities in the precedence diagramming method?

Finish-to-start (FS): An activity must finish before the successor can start



Start-to-start (SS): An activity must start before the successor can start



Finish-to-finish (FF): An activity must finish before the successor can finish



Start-to-finish (SF): An activity must start before the successor can finish

What are mandatory dependencies?



What are discretionary dependencies?

Mandatory: The order in which activities MUST be done, due to the
inherent nature of the work; also called "hard logic"



Discretionary: The order in which the organization has CHOSEN that activities be performed; also called "preferred," "preferential," or "soft logic"

What are external dependencies?



What are internal dependencies?

External: Dependencies based on the needs of a party OUTSIDE the project



Internal: Dependencies based on the needs of the project; may be under the control of the project team

What is a lag?



What is a lead?

Lag: Waiting time inserted between activities



Lead: How soon an activity can start before its predecessor activity is completed

What is a resource breakdown structure?

An organizational chart or table showing identified resources, organized by category and type

How does a schedule model differ from a schedule?

The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.



The project schedule is the output of the schedule model—this refers to the final, printed dates that make up the schedule that becomes the baseline and part of the project management plan

What is the critical path?



What is the near-critical path?

Critical: The longest path through the network diagram



Near-critical: The path closest in length to the critical path

How does the critical path help us manage the project?

It shows the project manager the shortest time in which the project can be completed



It shows the project manager where to focus his or her time



It is used in compressing or adjusting the schedule

Define total float, free float, and project float

Total float: The amount of time an activity can be delayed without delaying the project end date or an intermediary milestone



Free float: The amount of time an activity can be delayed without delaying the early start date of its successor(s)



Project float: The amount of time the project can be delayed without affecting the project's required end date

What are the two formulas for calculating float?

Late start - Early start
OR
Late finish - Early finish

What are the methods that can be used to compress a schedule?

Crashing



Fast tracking

What is crashing?

Adding or adjusting resources in order to compress the schedule while maintaining the original project scope

What is fast tracking?

Compressing the schedule by doing more critical path activities in parallel

What is the critical chain method?

A schedule network analysis tool that builds in buffers at critical milestones

What is reestimating?

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot

What is resource optimization?

Finding ways to adjust the use of resources

What is resource leveling?

A resource optimization technique that keeps the amount of resources used for each time period constant, resulting in a more stable level of resources and a longer project duration

What is resource smoothing?

A modified form of resource leveling, where resources are leveled only within the limits of the float of their activities, so the completion dates of activities are not delayed

What is the schedule baseline?

The approved version of the schedule model, along with any approved changes, used to measure project schedule performance

What are the main presentation formats for a schedule?

Network diagrams
Bar charts
Milestone charts

What do network diagrams show?

Dependencies (logical relationships) between activities



How project activities will flow from beginning to end



Network diagrams may also be used to determine the critical path

What do simple bar charts show?

Project schedule or project status

What do milestone charts show?

High-level project status

What is Monte Carlo analysis?

A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific cost



Also used in Perform Quantitative Risk Analysis to determine the overall level of risk on the project