• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/63

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

63 Cards in this Set

  • Front
  • Back

List the 6 processes in the Proj Time Mgmt ka

1 Define Activities
2 Sequence Activities
3 Estimate Activity Resources
4 Estimate Activity Durations
5 Develop Schedule
6 Control Schedule

Describe the Define Activities process in the Proj Time Mgmt ka

Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables.



Project work packages are typically decomposed into smaller components called activities.



Activities provide a basis for estimating, scheduling, executing, and monitoring and controlling the project work.

Describe the 3 inputs of the Define Activities process

1. Scope Baseline
2. Enterprise Environmental Factors
3. Organizational Process Assets

Describe the 4 tools/techniques for the Define Activities process

1. Decomposition
2. Rolling wave planning -
3. Templates
4. Expert Judgment

Describe the 3 outputs of the Define Activities process

1. Activity list
2. Activity attributes
3. Milestone List

Describe the Sequence Activities process in the Proj Time Mgmt ka

Sequence Activities is the process of identifying and documenting relationships among the project activities. It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule.

Describe the 5 inputs of the Sequence Activities process

1 Activity List
2 Activity Attributes
3 Milestone List
4 Project Scope Statement
5 Organizational Process Assets

Describe the 4 tools/techniques for the Sequence Activities process

1. Precedence Diagramming Method (PDM) - a method used in Critical Path Methodology (CPM) for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities
2. Dependency Determination
3. Applying Leads and Lags
4. Schedule Network Templates

Describe the 2 outputs of the Sequence Activities process

1. Project Schedule Network Diagrams - schematic displays of the project’s schedule activities and the logical relationships among them, also referred to as dependencies.
2. Project Document Updates

Describe the four types of dependencies or logical relationships in the Precedence Diagramming Method (PDM).

1. Finish-to-start (FS). The initiation of the successor activity depends upon the completion of the predecessor activity.
2. Finish-to-finish (FF). The completion of the successor activity depends upon the completion of the predecessor activity.
3. Start-to-start (SS). The initiation of the successor activity depends upon the initiation of the predecessor activity.
4. Start-to-finish (SF). The completion of the successor activity depends upon the initiation of the predecessor activity.

- In PDM, finish-to-start is the most commonly used type of precedence relationship.
- The start-to-finish relationship is rarely used.

Describe 3 three types of dependencies are used to define the sequence among activities.

1. Mandatory dependencies - those that are contractually required or inherent in the nature of the work. often involve physical limitations



2. Discretionary dependencies - soft logic. established based on knowledge of best practices within a particular application area



3. External dependencies- usually outside the project team’s control. For example, governmental environmental hearings may need to be held before site preparation can begin

Explain "leads" & "lags"

- A lead allows an acceleration of the successor activity. For example, on a project to construct a new office building, the landscaping could be scheduled to start 2 weeks prior to the scheduled punch list completion. This would be shown as a finish-to-start with a 2-week lead.



- A lag directs a delay in the successor activity. For example, a technical writing team can begin editing the draft of a large document 15 days after they begin writing it. This could be shown as a start-to-start relationship with a 15-day lag.

Describe the Estimate Activity Resources process in the Proj Time Mgmt ka

Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity.

Describe the 5 inputs to the Estimate Activity Resources process.

1. Activity List
2. Activity Attributes
3. Resource Calendars
4. Enterprise Environmental Factors
5. Organizational Process Assets

Describe the 5 tools/techniques to the Estimate Activity Resources process.

1. Expert Judgment
2. Alternatives Analysis
3. Published Estimating Data
4. Bottom-Up Estimating
5. Project Management Software

Describe the 3 outputs to the Estimate Activity Resources process.
1. Activity Resource Requirements
2. Resource Breakdown Structure
3. Project Document Updates
Describe the Estimate Activity Durations process in the Proj Time Mgmt ka

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated resources.

Describe the 7 inputs to the Estimate Activity Durations process.

1. Activity List
2. Activity Attributes
3. Activity Resource Requirements
4. Resource Calendars
5. Project Scope Statement
6. Enterprise Environmental Factors
7. Organizational Process Assets

Describe the 5 tools/techniques to the Estimate Activity Durations process.

1. Expert Judgment
2. Analogous estimating - uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project,
3. Parametric estimating - uses a statistical relationship between historical data and other variables (e.g., square footage in construction)
4. Three-Point Estimates (PERT)
5. Reserve Analysis

Describe the 2 outputs to the Estimate Activity Durations process.

1. Activity duration estimates - quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags.
2. Project Document Updates

Describe PERT and its 3 estimate types.

Program Evaluation and Review Technique (PERT) - uses three estimates to define an approximate range for an activity’s duration:
1. Most likely (tM).
2. Optimistic (t O). .
3. Pessimistic (tP). The activity duration is based on analysis of the worst-case scenario for the activity.

What is the formula to calculate expected activity in PERT?

PERT analysis calculates an Expected (tE) activity duration using a weighted average of the three estimates.

Describe the Develop Schedule process in the Proj Time Mgmt ka

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

Describe the 9 inputs to the Develop Schedule process.
1 Activity List
2 Activity Attributes
3 Project Schedule Network Diagrams
4 Activity Resource Requirements
5 Resource Calendars
6 Activity Duration Estimates
7 Project Scope Statement
8 Enterprise Environmental Factors
9 Organizational Process Assets
Describe the 8 tools/techniques to the Develop Schedule process.

1. Schedule Network Analysis - such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates analysis or other analyses.
2. Critical Path Method
3. Critical Chain Method
4. Resource Leveling
5. What-If Scenario Analysis
6. Applying Leads and Lags
7. Schedule Compression - shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives.
8. Scheduling Tool

Describe the 4 outputs to the Develop Schedule process.

1. Project Schedule
2. Schedule Baseline - a specific version of the project schedule developed from the schedule network analysis.
3. Schedule Data
4. Project Document Updates

Describe the Critical Path Method.

The critical path method calculates the theoretical early start and finish dates, and late start and finish dates, for all activities without regard for any resource limitations, by performing a forward and backward pass analysis through the schedule network.

What is "total float"?

Provides schedule flexibility and, may be positive, negative, or zero. On any network path, the schedule flexibility is measured by the positive difference between early and late dates, and is termed “total float.” Critical paths have either a zero or negative total float, A critical path is normally characterized by zero total float on the critical path.

Describe the Critical Chain Method.

Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources.



After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting critical path is known as the critical chain. The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty.

Describe Resource Leveling

-Applied to a schedule that has already been analyzed by the critical path method.


-used when shared or critical required resources are only available at certain times,


-Neccessary when resources have been over-allocated

Describe What-If Scenario Analysis

-What if ‘X’ happens?”


-uses the schedule to compute the different scenarios, such as delaying a major component delivery


-most common technique is Monte Carlo Analysis

Describe the 2 schedule compression techniqes.

1. Crashing - cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression Examples of crashing could include approving overtime, bringing in additional resources.
2. Fast tracking - A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel.

Describe 3 possible formats for representing project schedules

1. Milestone charts - similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces.
2. Bar charts - show activity start and end dates, as well as expected durations.
3. Project schedule network diagrams - contain activity date information, usually show both the project network logic and the project’s critical path schedule activities.

Describe the Control Schedule process in the Proj Time Mgmt ka

Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline. Schedule control is concerned with:
- Determining the current status of the project schedule,
- Influencing the factors that create schedule changes,
- Determining that the project schedule has changed, and
- Managing the actual changes as they occur.

Describe the 4 inputs of the Control Schedule process.

1 Project Management Plan
2 Project Schedule
3 Work Performance Information
4 Organizational Process Assets

Describe the 8 tools/techniques of the Control Schedule process.

1. Performance Reviews - measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress.
2. Variance Analysis - Schedule performance measurements (SV, SPI) are used to assess the magnitude of variation to the original schedule baseline. The total float variance is also an essential planning component to evaluate project time performance.
3. Project Management Software
4. Resource Leveling
5. What-If Scenario Analysis
6. Adjusting Leads and Lags
7. Schedule Compression
8. Scheduling Tool

Describe the 5 outputs of the Control Schedule process.

1. Work Performance Measurements (SV & SPI)
2. Organizational Process Assets Updates
3. Change Requests
4. Project Management Plan Updates
5. Project Document Updates

What does Define Activity mean and include?

The process of identifying the specific actions to be performed to produce the project deliverables
Activity list: is a tabulation of activites to be included on project schedule
Activity attributes: shedule related information about activity
Milestone list: Significant event with no duration attached to it

What are mandetory dependecies

Are inherent in the nature of the work
"Physical constraints"

Descretionary dependencies
Defined by the project team as examples of good practice
"Good practice"
External dependencies

Relationships between project and non–project activities
Non project – i.e government must make a ruling before can act

What does estimate activity duration mean?

The process of approximating the number of work periods needed to complete individual activities with estimated resources

What does develop schedule mean?
Process of analyzing the activity sequences, durations, resource requirements and schedule constraints to create the project scheule model
CPM what is it and what does it determine?

Critical Path Method
The series of activities that determine the earliest time a project can be compleated
Determines the total project duration by taking the longest path through the network diagram

Critical Chain Method
Application of Theory of Constraints. Considers limited resources and includes buffers to protect project compleation date
Resource Leveling. What is it and When used?

Applied to a schedule that has already been analyzed by CPM.
Used when shared or critical resources are only available at certian times

Resource Smoothing
Adjusts the activities of a schedule model such that resource requirements do not exceed predefined limits. Does not change critical path.
Schedule compression – two ways
Shortens the project schedule without changing the project scope
1) Crashing
2) Fast tracking
Crashing
Increase resource allocation to shorten activity duration
Fast Tracking
Activity overlap
Def. Activity
An element of work in an WBS that has an expected duration, cost and resource requirements
What is activity also called?

Task

What is a task also called?
Activity
What does a backward pass determine?

The late start and late finish dates for each activity

What does effort refer to in time management?

Number of workdays or work hours to complete a task

What does forward pass determine?

early start dates and early finish dates

A display that shows activites and thier start and finish dates, callender format
Gnatt chart

PERT avearge

(optimistic + 4*,most likely + pessimistic)/6

Rolling wave planning

a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS

Finish to Start

Frame Floor, THEN pour concrete

Finish to Finish

Last student finishes exam, THEN indivudualtor can collect exams

Start to start

Marathon starts, THEN GPS tracking can start

Start to Finish

Delivery Tracking Report THEN Last delivery