Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
63 Cards in this Set
- Front
- Back
List the 6 processes in the Proj Time Mgmt ka |
1 Define Activities |
|
Describe the Define Activities process in the Proj Time Mgmt ka |
Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables.
Project work packages are typically decomposed into smaller components called activities.
Activities provide a basis for estimating, scheduling, executing, and monitoring and controlling the project work. |
|
Describe the 3 inputs of the Define Activities process
|
1. Scope Baseline |
|
Describe the 4 tools/techniques for the Define Activities process |
1. Decomposition |
|
Describe the 3 outputs of the Define Activities process
|
1. Activity list |
|
Describe the Sequence Activities process in the Proj Time Mgmt ka |
Sequence Activities is the process of identifying and documenting relationships among the project activities. It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. |
|
Describe the 5 inputs of the Sequence Activities process
|
1 Activity List |
|
Describe the 4 tools/techniques for the Sequence Activities process
|
1. Precedence Diagramming Method (PDM) - a method used in Critical Path Methodology (CPM) for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities |
|
Describe the 2 outputs of the Sequence Activities process
|
1. Project Schedule Network Diagrams - schematic displays of the project’s schedule activities and the logical relationships among them, also referred to as dependencies. |
|
Describe the four types of dependencies or logical relationships in the Precedence Diagramming Method (PDM). |
1. Finish-to-start (FS). The initiation of the successor activity depends upon the completion of the predecessor activity. |
|
Describe 3 three types of dependencies are used to define the sequence among activities. |
1. Mandatory dependencies - those that are contractually required or inherent in the nature of the work. often involve physical limitations
|
|
Explain "leads" & "lags"
|
- A lead allows an acceleration of the successor activity. For example, on a project to construct a new office building, the landscaping could be scheduled to start 2 weeks prior to the scheduled punch list completion. This would be shown as a finish-to-start with a 2-week lead.
|
|
Describe the Estimate Activity Resources process in the Proj Time Mgmt ka
|
Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. |
|
Describe the 5 inputs to the Estimate Activity Resources process.
|
1. Activity List |
|
Describe the 5 tools/techniques to the Estimate Activity Resources process.
|
1. Expert Judgment |
|
Describe the 3 outputs to the Estimate Activity Resources process.
|
1. Activity Resource Requirements
2. Resource Breakdown Structure 3. Project Document Updates |
|
Describe the Estimate Activity Durations process in the Proj Time Mgmt ka
|
Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated resources. |
|
Describe the 7 inputs to the Estimate Activity Durations process.
|
1. Activity List |
|
Describe the 5 tools/techniques to the Estimate Activity Durations process.
|
1. Expert Judgment |
|
Describe the 2 outputs to the Estimate Activity Durations process.
|
1. Activity duration estimates - quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags. |
|
Describe PERT and its 3 estimate types.
|
Program Evaluation and Review Technique (PERT) - uses three estimates to define an approximate range for an activity’s duration: |
|
What is the formula to calculate expected activity in PERT? |
PERT analysis calculates an Expected (tE) activity duration using a weighted average of the three estimates. |
|
Describe the Develop Schedule process in the Proj Time Mgmt ka
|
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. |
|
Describe the 9 inputs to the Develop Schedule process.
|
1 Activity List
2 Activity Attributes 3 Project Schedule Network Diagrams 4 Activity Resource Requirements 5 Resource Calendars 6 Activity Duration Estimates 7 Project Scope Statement 8 Enterprise Environmental Factors 9 Organizational Process Assets |
|
Describe the 8 tools/techniques to the Develop Schedule process.
|
1. Schedule Network Analysis - such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates analysis or other analyses. |
|
Describe the 4 outputs to the Develop Schedule process.
|
1. Project Schedule |
|
Describe the Critical Path Method.
|
The critical path method calculates the theoretical early start and finish dates, and late start and finish dates, for all activities without regard for any resource limitations, by performing a forward and backward pass analysis through the schedule network. |
|
What is "total float"? |
Provides schedule flexibility and, may be positive, negative, or zero. On any network path, the schedule flexibility is measured by the positive difference between early and late dates, and is termed “total float.” Critical paths have either a zero or negative total float, A critical path is normally characterized by zero total float on the critical path. |
|
Describe the Critical Chain Method. |
Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources.
After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting critical path is known as the critical chain. The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty. |
|
Describe Resource Leveling |
-Applied to a schedule that has already been analyzed by the critical path method. -used when shared or critical required resources are only available at certain times, -Neccessary when resources have been over-allocated |
|
Describe What-If Scenario Analysis
|
-What if ‘X’ happens?” -uses the schedule to compute the different scenarios, such as delaying a major component delivery -most common technique is Monte Carlo Analysis |
|
Describe the 2 schedule compression techniqes.
|
1. Crashing - cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression Examples of crashing could include approving overtime, bringing in additional resources. |
|
Describe 3 possible formats for representing project schedules |
1. Milestone charts - similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces. |
|
Describe the Control Schedule process in the Proj Time Mgmt ka
|
Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline. Schedule control is concerned with: |
|
Describe the 4 inputs of the Control Schedule process.
|
1 Project Management Plan |
|
Describe the 8 tools/techniques of the Control Schedule process.
|
1. Performance Reviews - measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress. |
|
Describe the 5 outputs of the Control Schedule process.
|
1. Work Performance Measurements (SV & SPI) |
|
What does Define Activity mean and include?
|
The process of identifying the specific actions to be performed to produce the project deliverables |
|
What are mandetory dependecies
|
Are inherent in the nature of the work |
|
Descretionary dependencies
|
Defined by the project team as examples of good practice
"Good practice" |
|
External dependencies
|
Relationships between project and non–project activities |
|
What does estimate activity duration mean?
|
The process of approximating the number of work periods needed to complete individual activities with estimated resources |
|
What does develop schedule mean?
|
Process of analyzing the activity sequences, durations, resource requirements and schedule constraints to create the project scheule model
|
|
CPM what is it and what does it determine?
|
Critical Path Method |
|
Critical Chain Method
|
Application of Theory of Constraints. Considers limited resources and includes buffers to protect project compleation date
|
|
Resource Leveling. What is it and When used?
|
Applied to a schedule that has already been analyzed by CPM. |
|
Resource Smoothing
|
Adjusts the activities of a schedule model such that resource requirements do not exceed predefined limits. Does not change critical path.
|
|
Schedule compression – two ways
|
Shortens the project schedule without changing the project scope
1) Crashing 2) Fast tracking |
|
Crashing
|
Increase resource allocation to shorten activity duration
|
|
Fast Tracking
|
Activity overlap
|
|
Def. Activity
|
An element of work in an WBS that has an expected duration, cost and resource requirements
|
|
What is activity also called?
|
Task |
|
What is a task also called?
|
Activity
|
|
What does a backward pass determine?
|
The late start and late finish dates for each activity |
|
What does effort refer to in time management?
|
Number of workdays or work hours to complete a task |
|
What does forward pass determine?
|
early start dates and early finish dates |
|
A display that shows activites and thier start and finish dates, callender format
|
Gnatt chart
|
|
PERT avearge |
(optimistic + 4*,most likely + pessimistic)/6 |
|
Rolling wave planning |
a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS |
|
Finish to Start |
Frame Floor, THEN pour concrete |
|
Finish to Finish |
Last student finishes exam, THEN indivudualtor can collect exams |
|
Start to start |
Marathon starts, THEN GPS tracking can start |
|
Start to Finish |
Delivery Tracking Report THEN Last delivery |