• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/138

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

138 Cards in this Set

  • Front
  • Back

1. T/F - MRP uses the lot size key in the material master record to determine the quantity of a planned order.

1. True
2. T/F - BOMs are created and maintained as multi-level bills.
1. False
The base quantity, in the BOM header, specifies to which amount of the finished product the item quantities refer.
1. True
4. What is the difference between regenerative MRP and net change MRP? (2)
1. Regenerative planning wipes existing schedules completely out
2. Net change re-plans it by looking at the differences from the previous runs
5. What is a product group?
1. It is a forecast group that sums all lower level components.
6. List the options for running MRP (4)
1. Total planning
2. Single-item planning Multilevel
3. Single-item planning Single-level
4. Single-item planning Interactive
7. What is the difference between the stock requirements list and the MRP list? (2)
1. Stock requirements list is dynamic
2. MRP is a snapshot.
8. What is the difference between MRP and Consumption Based Planning? (2)
1. Consumption is based on historical consumption (The Past).
2. MRP looks to the future.
9. What is the result of an order completion confirmation?
1. The confirmed quantity, the CNF (Finally Confirmed) status, and the actual costs are written in the production order.
10. What happens, on the Stock Requirements List, when a planned order is converted to a production order: (2)
1. For the finished product, the planned order goes away and production order replaces
2. For the components, the dependent requirement goes away and its shown as reserved.
11. What is a work center? (3)
1. It specifies where production ultimately takes place.
2. It is a specific geographic location in the plant.
3. It may refer to a specific machine or department in a plant.
12. What is a routing? (2)
1. Routings contain the steps that are necessary for production.
2. Routings include the relevant operations, sequence in which the routings occur, and work centers at which the operations are to be executed
13. What transactions debit (Charge It) a production order? (3)
1. Material withdraw
2. Confirmation
3. Sometimes Settlement
14. What transactions credit a production order?
1. Good Receipt
2. Settlement (if it takes longer)
15. T/F - Master data can be created centrally.
1. True
16. T/F - Master data, such as a material master record, is only used in a single business process.
1. False
17. T/F - Master data is organized into views or data categories which are assigned to organizational elements.
1. True
18. T/F - In a material master record, data defined at the client level can be used by all plants.
1. True
19. T/F - In a vendor master record, data defined at the client level can only be used by a single company code.
1. False
20. T/F - A company code is the highest organizational element.
1. False: Client is
21. T/F - A purchase requisition can be created manually or automatically by MRP.
1. True
22. T/F - An account assignment object determines the process used to procure a material or service.
1. True
23. T/F - If an enterprise uses the Cross-Plant Purchasing scenario, then a purchasing organization procures material for all company codes within a client.
1. False
24. T/F - The Stock Overview displays quantities posted for a particular stock type for each organizational level.
1. True: They are as follows: Client company code, plant , storage location
25. T/F - Conditions in a purchase order (pricing conditions) determine the account to be charged at the time of goods receipt.
1. False: Conditions sets pricing, taxes and discounts (the attributes that are used to determine monetary value) so at good receipt it will post to GR/IR and Purchase Order History
26. T/F - Consumable materials are materials or services procured specifically for an account assignment object.
1. True
27. T/F - A material master record can be used by all of the Logistics modules.
1. True
28. T/F - If a material is stored in multiple plants, then a material master record must be maintained for each plant.
1. True
29. T/F - The data maintained in a material master may be valid for more than one organizational level.
1. True
30. T/F - The GR/IR account is posted to at goods receipt and invoice receipt.
1. True
31. What is a record of a transaction?
1. Document
32. What are the effects of Invoice Verification? (3)
1. Creates a line on purchase order history,
2. Accounting document,
3. Reverses provisions Figure 112
33. What are the data categories of a vendor master record? (3)
1. General Data (Client)
2. Accounting (Company code) data
3. Purchase Organization Data
34. What are the effects of a Goods Receipt? Figure ? (6)
1. Material Quantity Document
2. Accounting Value document
3. Purchasing – Updates the PO history
4. QM (if active) – Creates an inspection lot
5. Warehouse Management (if active) – Creates a transfer requirement
6. Generating output (if active) – GR slip or pallet label
35. What two types of master data are linked by a purchasing-info record? (2)
1. Vendor
2. Material
36. List the three stock types that indicate the usability of a material.
1. Unrestricted
2. Quality Inspection
3. Blocked
37. What are the control functions of a movement type? (2)
1. Automatic Account Determination
2. Determines the screen layout for entering documents or updating quantity fields.
38. What are the organizational units relevant for material planning? (3)
1. Client
2. Plant
3. Storage Location
39. T/F - Basic data in the material master is applicable to the entire company, and is stored at the plant level.
1. False: It is stored at the Client level.
40. What master data is relevant for material planning? (3)
1. Material
2. Bill of Material
3. Routings
41. What three material master views are relevant for planning and are specific to the Plant?
1. Material Requirements Planning (MRP)
2. Execution (Work Scheduling)
3. Accounting
42. At what organizational unit are the MRP and accounting view relevant? (1)
1. Plant
43. What is the purpose of MRP type?
1. Specifies how a material should be planned
a. MRP
b. Consumption based planning
c. No Planning
44. What is the purpose of Lot size?
1. Determines the quantity of each of the procurement proposals.
45. What is the purpose of Procurement type?
1. Controls how a material is to be procured
a. In house (internal)
b. External procurement
c. Internal and External
46. What is the purpose of In-house production time?
1. Specifies how long procurement will last.
47. What is the purpose of Safety stock?
1. Safety stock is used to safeguard the supply chain against uncertain influencing factors.
48. What is the purpose of Strategy group?
1. Control the behavior of planned independent requirements.
49. What is the purpose of Availability check?
1. Control of the Available to Promise (ATP) check.
50. What are the three procurement types? (3)
1. External
2. Internal
3. External and Internal
51. For externally procured materials, MRP can produce? (3)
1. Planned orders
2. Purchase requisition
3. Schedule lines
52. Name two things that affect consumption-based planning. (2)
1. Past consumption
2. Safety stock
53. What does the base quantity in a BOM refer to? (1)
1. The base quantity, in the BOM header, specifies the amount of the finished product that the item quantities refer to.
54. Are all BOMs single-level?
1. Yes
55. What does the BOM usage determine? (1)
1. BOM usage determines the business applications for which a BOM can be used.
56. What does the BOM status determine?
1. Controls whether the BOM is active for particular applications.
57. List the item categories in BOMs? (4)
1. Stock
2. Non-stock
3. Variable-size
4. Document
58. What does item category determine in the context of a BOM? (2)
1. Specifies what kind of item you are dealing with.
2. Influences the processing of the component.
59. What is the purpose of a routing?
1. Contains the steps that are necessary for production.
60. How are the BOM and Routing master data linked?
1. Material Number
2. Task List Group
61. What are the steps in the material planning process? (4)
1. CO/PA Profitability Analysis: Revenue and Sales Plans
2. SOP Sales and Operations Planning: Sales and Production Plans
3. MPS Master Production Scheduling: Demand program and Adjusted Master Plan.
4. MRP Material Requirements Planning: Dependent Requirements, Planned Production, and Procurement Plan.
62. What can SOP be used for? (3)
1. Sales Planning
2. Production Planning
3. Feasibility estimates
63. Define product group.
1. It groups together products with similar characteristics. A product family.
64. How is planning done with product groups?
1. Product groups help in the planning process by grouping products with similar planning characteristics.
65. Explain the concept of and options for disaggregation of product groups. (4)
1. It is planning data at the material level
2. Disaggregate the production plan of product group 1.
3. Disaggregate the sales of product group 1.
4. Disaggregate the sales plans of all the product groups down to the materials.
66. When a production plan is transferred to demand management, what are created?
1. Planned Independent requirements.
67. What are the two broad types of planning? (2)
1. MRP
2. Consumption-based
68. What forms the basis for planning for each type of planning? (2)
1. MRP: Based on independent requirements.
2. Consumption-based: Based on past consumption.
69. Describe two features of MRP? (2)
1. MRP can be run at the plant level.
2. MRP will first use forward scheduling to calculate the requirement’s date.
70. Assume a BOM has a component that is externally procured. What are the options for procurement proposals that you have when you run MRP? (4)
1. Create purchase requisitions
2. Create planned orders
3. Create schedule lines
4. Create purchase orders only in the opening period
71. Describe the MRP process for in-house procurement; for external procurement.
1. In-house procurement: The system creates planned orders for the planning of production quantities. When planning is complete, planned orders can be converted into production orders.
2. External procurement: The system creates either a planned order, or directly creates a purchase requisition. When planning is complete, planned orders can be converted into purchase requisitions, then into purchase orders.
72. Describe multilevel MRP. (2)
1. Multileveled planning takes place over all BOM levels. Dependent requirements are thus also planned.
2. In Single-level planning it is only the header material that is planned.
73. How does MRP determine that materials must be acquired?
1. Through the execution of a Net Requirements Calculation. It determines if a material shortage exists.
74. The supply side of net requirements planning includes what four things? (4)
1. Stock
2. Firmed purchase requisitions
3. Purchase orders
4. Safety Stock
75. What makes up the supply in the net requirements calculation?
1. Procurement Proposal
2. Firmed Receipts
3. Firmed Planned Orders
4. Firmed Purchase
5. Requisitions
6. Stock
76. What makes up the demand in the net requirements calculation?
1. Sales Orders
2. Planned Independent Requirements
3. Secondary requirements
4. Reservations
77. Describe the difference between NEUPL, NETCH, NETPL.
1. NEUPL: Regenerative planning – Planning of all MRP relevant materials
2. NETCH: Net Change for Total Horizon – Planning all materials which have undergone a change relevant to the planning run.
3. NETPL: Net Change for Planning Horizon – Planning all materials for which MRP relevant changes have been made in the planning horizon. Planning within the planning horizon only.
78. What are the control parameters in MRP? (5)
1. Processing key: Define the planning type
2. Create purchase requisitions: Only relevant for materials that are procured externally.
3. Create schedule line: Only relevant for materials that are procured externally.
4. Create MRP list: Always, Never, only with certain Exception Messages
5. Planning mode: Defines if existing planning data: Simply be adjusted, BOMs and routings be re-exploded, or planning start from very beginning.
79. What is the difference between the stock/requirements list and the MRP list? (2)
1. Stock/requirements list contains up-to-date information on the current status of stocks
2. MRP list depicts the result of the latest planning run and is therefore static.
80. What happens when you convert a planned order to a production order?
1. The dependent requirements are transferred to order reservations.
81. The material type, the most important value assigned, of a material determines what? (5)
1. Default procurement type
2. Master Number – how assignment is carried out.
3. Material views available – the screens that appear in the material master record.
4. Relevant general ledger accounts.
5. Business processes and functions allowed – department-specific data that can be maintained.
82. What are five ways to create sales plans in SOP Planning Table? (5)
1. Transferring data from the Sales Information System (SIS.)
2. Transferring data from the Controlling/Profitability Analysis Module COPA
3. Copy from another product group
4. Using history to forecast future sales
5. Manually enter
83. Name two attributes for consumption-based planning? (2)
1. It is based on historical rates of consumption
2. It is appropriate for low value materials
84. Give four examples of Material Types:
1. Raw Materials
2. Operating Supplies
3. Semi-finished Products
4. Finished Products
85. BOMs are used in what four processes?
1. Material Requirements Planning
2. Production
3. Procurement
4. Product Costing
86. The BOM contains the assemblies or components, that are to be included in the ___________ of a material.
1. Production
87. What are the five ways a SOP Production Plan can be created?
1. Synchronously to sales (equal to sales plan)
2. Target stock level
3. Target days supply
4. Inventory to Zero (reduces inventory on-hand to zero balance and then plans equal to sales plan)
5. Manual entry
88. What are the three Production Planning Strategies?
1. Make-to-Stock
2. Subassembly
3. Make-to-order
89. How can a MRP (Planning) Run be carried out? (4)
1. Total Planning for planning of all materials of one or several plants
2. Multilevel for planning of a material’s BOM
3. Single-level for planning of a material
4. Interactive for interactive single-level planning.
90. What is Multilevel Backward Scheduling?
1. System calculates the necessary start dates based on a predefined end date.
91. If a planned order is converted into a production order, the _________ _________ are transferred to order reservations.
1. Dependent Requirements
92. If MRP discovers shortage quantities, ___________ ___________ are generated.
1. Procurement Proposals
93. What is MPS -Master Production Scheduling?
It is a form of MRP that concentrates planning on the parts or products that have the great influence on company profits or which dominate the entire production process by taking critical resources
94. List master data for manufacturing execution. (5)
1. Material Master: Procurement Type = In-house Production (X,E)
2. BOMs
3. Work center/Resource: Are assigned in the Routing of the operations.
4. Task List: Can be Routings, Rate Routings, or Master Recipes
5. Production Resource Tools (PRT): Are assigned in the Routing of the operations.
95. What are the application modules that integrate with Manufacturing Execution? (6)
1. Inventory management
2. Quality management
3. Financial accounting
4. Controlling
5. Sales and distribution
6. Project systems
96. What data is stored in a work center? (5)
1. Basic data
2. Capacities
3. Scheduling
4. Costing
5. Standard Parameters
97. The work center master data includes: (7)
1. Basic data
2. Default values
3. Standard values key
4. Cost
5. Capacities
6. Scheduling
7. Cost Center
98. Standard operating times are defined in what?
1. Routing
99. What is the purpose of a routing?
1. Lists the sequence of steps for producing a material. That is, the corresponding operations, their sequence and the work centers in which these operations are to be executed.
100. Elements of routings include: (6)
1. Operations
2. Operation sequences
3. Usage
4. Time elements
5. Work Centers
6. Component Allocations
101. How do work centers interact with routings?
1. By entering a standard value key, a resource is assigned standard values for operations in routings.
102. BOMs are used in: (4)
1. MRP
2. Production
3. Product costing
4. Procurement
103. How do BOMs interact with routings?
1. Components of a BOM are assigned to certain operations in the routing.
104. SAP BOMs can be transferred to SAP Advanced Planner and Optimizer (APO) in the form of:
1. Production Process Models (PPM)
105. What accounts are affected when materials are issued to a production order? (2)
1. Raw material stock account
2. Consumption account
106. What is the structure of a production order? (5)
1. Header
2. Operations
3. PRT
4. Costs
5. Settlement rule
107. What are the steps in production order processing? (13)
1. Order request – Planned Order
2. Order creation – Production order
3. Availability checks – Material/Capacity
4. Machine reservation – Loading Capacity
5. Order release
6. Order print
7. Material Staging
8. Material withdrawal
9. Confirmation (CR. Order)
10. WIP Determination
11. Goods receipt
12. Variance calc.
13. Order settlement
108. What three processing activities are generally periodic for Cost Object Controlling?
1. WIP Determination
2. Variance Calculation
3. Settlement
109. When are planned costs calculated for a production order?
1. Costs are determined at operation level and submitted at the order header level.
110. What occurs when planned orders are converted to production orders?
1. The system will display the production order header with production order number.
111. Why does a production order need to be released?
1. Order release is necessary so that subsequent processes may occur.
112. What can be performed after order release? (3)
1. Printing the shop floor documents
2. Component withdrawal
3. Order confirmations
113. When are availability checks performed? (2)
1. Order Creation
2. Release
114. In manufacturing execution, the availability check, checks for what? (3)
1. Components
2. Capacities
3. PRTs
115. How are material components assigned in routings and what is the default assignment? (2)
1. Component assignment is dealt with in the Routing.
2. The default assignment is to the first operation.
116. What are the effects of a goods issue? (6)
1. Reservation is reduced
2. Quantity and value in material master is updated
3. Consumption account is debited
4. Material document created
5. CO document created
6. FI document is created
117. What are order confirmations used for?
1. They are used for entering activities carried out within a company for an order.
118. What are the effects of confirmations? (3)
1. It declares the quantity that is produced, the quantity that is scrapped and the quantity that requires reworking.
2. It is also about confirming the total activity hours put in to producing the sub-assembly or assembly thereby deriving the order costs through activity based costing procedures.
3. And it is also about recording the personnel data responsible in producing the stock.
119. How are variances calculated?
1. The difference of Actual Cost and Planned Cost is Variance
120. In Cost Object Controlling (COC), order settlement does what? (2)
1. Debits the stock account
2. Credits the order
121. Explain the settlement process.
1. Settlement makes a Financial and CO posting for variances. The order/cost collector controlling object is debited/credited for the variance to bring its balance to zero.
122. What are the Movement Type codes for Goods Issue and Goods Receipt?
1. 261
2. 101
123. Explain activity types. (3)
1. Classifies the activities that are to be performed within a company by one or several cost centers.
2. Classifies the activities performed or produced by a cost center.
3. The costs of these resources need to be allocated to the receivers of the activity.
124. Can activity types be used with any cost center?
1. Yes: However, you can restrict the use of the activity type to certain types of cost centers by entering the allowed cost center categories in the activity type master record.
125. Explain DAA.
1. Direct Activity Allocation deals with the measurement, posting, and allocation of an organizational activity.
126. What types of objects can be senders and receivers in DAA?
1. When entering a direct activity allocation:
i. Enter the cost center that provides the activity (sender cost center).
ii. The object that receives the activity (receiver)
127. What is required to complete a DAA transaction?
1. An Activity Type
128. Explain commitments. (3)
1. Costs to be incurred in the future for materials and services
2. Created in the Purchasing function of MM.
3. Is recorded automatically when you assign an overhead order to a purchase order.
129. What are the three phases of product cost accounting?
1. Product cost planning: Estimate the costs to produce goods or services
2. Cost object controlling: Collects costs incurred during production of a product or service using cost objects such as production orders.
3. Actual costing and material ledger: Provides actual costs for wach material at the end of the period.
130. What is calculated during period-end closing? (2)
1. Period-end closing calculates the value of goods still in production (work in process)
2. and the variances between the cost estimate and the actual costs.
131. What is the difference between marking a standard cost estimate and releasing a standard cost estimate? (2)
1. Marking enables the results of the standard cost to be updated as the Future Standard Price in the material master.
2. Releasing a standard cost estimate enables the Future Standard Price to be updated as the Current Standard Price and the Current Planned Price in the Material Master.
132. What are the standard price and standard cost used for?
1. Standard Price: Used to valuate goods movements within SAP ERP and to valuate inventories.
2. Standard Cost: Used to update the standard price.
133. Describe the process for updating the standard price. (3 Steps)
1. Analyze the costs
2. Marking
3. Releasing
134. List the six true cost objects.
1. Cost Centers
2. Real Internal Orders
3. Real Projects
4. Networks
5. Cost Objects
6. Profitability Segments
135. What does a Goods Issue to a cost center create in FI?
1. A transaction that debits a material consumption expense account and credits a material stock (inventory) account.
136. What three things are needed to enter a direct activity allocation?
1. Sender Cost Center
2. Receiver
3. Activity Type
137. What is a Price Update?
1. Marking and releasing a standard cost estimate updates the standard price for the material in the material master record. This results in the inventory being revaluated.
138. What are the prerequisites that must be met before a standard cost estimate can be marked or released? (3)
1. Standard cost estimate must be free of errors (status KA, costed without errors).
2. The company code and period in which the standard cost estimate can be marked with a set Costing Variant are entered in the authorization for a marking.
3. You can release a standard cost estimate only once per period